homepage home
subscribe to Southwest Contractor magazine subscribe
newsletters free e-newsletter
advertise
industry jobs industry jobs
Mcgraw Hill Construction
Southwest Contractor Logo
Order Your RISK FREE Subscription
Research Cube Offices on the north and west sides of ASU’s new lab building have interior windows that allow light to pass through into corridors and other interior spaces.
Photo: HDR/Ehrlich Architects

New Science Lab Uses Ample Green Systems

The $109-million ISTB IV lab building at Arizona State University uses a flexible mechanical system to achieve its sustainability goals

share:
print email comment
text size: A A

Because laboratory buildings can consume up to 10 times more energy than office buildings, Arizona State University needed efficient systems to achieve its sustainability goals for the new seven-story Interdisciplinary Science and Technology Building IV on its Tempe, Ariz., campus.

Stout Building Nearly 18,000 cubic yards of concrete have been placed in the seven-story ISTB IV building to date. Science lab experiments will require a building with low vibration transfer.
Photo: Sundt Construction
Stout Building Nearly 18,000 cubic yards of concrete have been placed in the seven-story ISTB IV building to date. Science lab experiments will require a building with low vibration transfer.
----- Advertising -----

Using strategies such as variable exhaust and intelligent sensors, the structure, now under construction, is modeled to use 41% less energy than a typical research lab, says Mohammad Madjidi, ASU's senior project manager.

The university committed to LEED Silver or greater, but it also has its own set of sustainable guidelines. “They are a supplement to the LEED process to clarify those areas of construction that best reflect the university's sustainability practices, goals and desired outcomes for high-performance buildings,” Madjidi says.

The 294,000-sq-ft building will bring together the Fulton Schools of Engineering with the School of Earth and Space Exploration so that the engineers who build scientific tools can co-locate and interact on a daily basis with the scientists who use the tools for research.

In a similar spirit, members of the project team also co-located during much of the pre-construction phase beginning in early 2009. Design architect Ehrlich Architects of Los Angeles and construction manager-at-risk Sundt Construction of Tempe moved key personnel into architect-of-record HDR Inc.'s Phoenix office to share Revit and other BIM drawings. “It allowed us to collaborate, check each other's work and divvy up tasks in far more specific ways,” says Mathew Chaney, design project manager with Ehrlich.

Just as the team was wrapping up the construction documents, the state of Arizona abruptly put the project on hold due to the recession. As a result, groundbreaking didn't occur until March 2010. “While the delay didn't help ASU with its research space needs, it did help with making the project more affordable by taking advantage of the market,” Madjidi says.

The guaranteed maximum price for the building dropped by $25 million to $109 million once the project re-started. Completion is scheduled for May 2012.

Nearly 25% of the budget is for the construction of the complex mechanical systems, says Ryan Abbott, Sundt's project director. “In a typical wet lab, you get close to 15 air changes in a lab per hour, but this building seeks to reduce those down to four or five.” Air control valves on fume hoods are linked to occupancy sensors so that a hood is not needlessly running at full power when there is no researcher nearby to protect.

Enhanced air sensors also dictate whether an increase in air changes is necessary by monitoring various gases. “We also used energy heat/cool recovery systems in the building. Because you are using so much single-pass air, the cooling load of bringing desert air into the building is really an enormous expense,” says Michael Jackson, vice president with HDR.

Labs with high air usage were placed adjacent to each other and near massive air exhaust shafts that run the full height of the building on two sides of the cast-in-place concrete structure. With each air change estimated to cost $4.28 in this building, according to Abbott, these strategies will save both energy and money.

The most complex labs, including a metal-free space for experiments that involve highly corrosive acids, are located in a basement level. The first and second floors are primarily public and gallery spaces for the display of meteorites and other rocks. The remaining floors contain offices, classrooms and additional lab space.

The building requires separate exhaust strategies based on the types of chemicals used in the labs. The team devised four exhaust systems: galvanized duct, stainless steel duct, stainless with the addition of a wash-down component and, for the corrosive labs, fiberglass reinforced plastic duct, Jackson says.

Nearly 30,000 utility hangers were incorporated into the BIM model to ensure there would be space to hang the large amount of ductwork and piping needed, says Brian Wieneke, project manager with mechanical contractor Dynamic Systems Inc., Austin, Texas. These points were then transferred to a laser total station, which allowed installers to place rod anchors into the formwork prior to the deck pours. “This was a huge time saver for the install crews,” Wieneke says.

BIM also helped subcontractor crews limit construction waste by facilitating pre-assembly of large sections of sheet metal and piping, Abbott says. Subcontractors are working with BIM models to drive computer-controlled manufacturing equipment for fabrication.

The pieces are assembled in the factory into 20-ft to 30-ft subassemblies, which are then transported to the site and installed. Abbott says that offsite pre-manufacturing enhances efficiency and safety, since workers are spending less time reaching above their heads to install pipe at the jobsite.

With these strategies, the project is currently on track to receive LEED Gold certification.

----- Advertising -----
Dodge Reports

Below is a brief listing of Projects Bidding in the South West. Click on any project to get Dodge Report, Plans and Specifications.

Click Here to See More Projects in the South West

Blog: From multiple ENR Southwest Bloggers
Our new blog delivers the latest project and people news, opinions and insights from the jobsite to the boardroom from the editors.
Reader Photos
Photos from Southwest Contractor Photo Showcase
Dodge Lead Center
FIND LOCAL
CONSTRUCTION PROJECTS
Search by Project Type & State



----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.