State Route 101L High-Occupancy Vehicle Lanes, Phoenix
This design-build project team delivered 30 miles of HOV lanes, widened five bridges and reconstructed eight on- and off-ramps in just 274 days, a full 13 months faster than the original schedule dictated. The team divided the project into segments so that the most congested areas could be completed first to relieve traffic backups. Design review was streamlined to package submittals based on sub-segment and project discipline, allowing the team to process 472 design submittals with a lightning fast average review time of 3.2 days. Teamwork was promoted through the formation of task forces that integrated designers with construction staff. Wireless paving and intelligent compaction equipment helped increase efficiency. On average, the team designed and built 1.5 lane-miles every week and cut $15.5 million from the original budget.
Key Players
Contractor: Kiewit/Sundt Joint Venture, Phoenix
Owner: Arizona Dept. of Transportation, Phoenix
Lead Design: Parsons Transportation Group, Tempe, Ariz.
Segment 2 Design: URS Corp., Phoenix
Subcontractors: Contractors West, Mesa, Ariz.; Combs Construction, Phoenix; Commercial Metals Co., Mesa, Ariz.; RGG United Contractors, Glendale, Ariz.; Advanced Concrete Sawing and Sealing, Mesa, Ariz.; Roadsafe Traffic Systems, Phoenix; Land-Tech Landscape Construction, Glendale, Ariz.
Submitted by Kiewit/Sundt Joint Venture

Sign in to Comment
To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.