Massive Arizona Power Plant Built With Time, Money to Spare

Text size: A A
[ Page 1 of 2 ]

Photo by Helicopter Photos
Coolidge Generating Station
Photo courtesy TIC - The Industrial Co.
Coolidge Generating Station
----- Advertising -----

Best Industrial/Manufacturing Project: Coolidge Generating Station 

This 512-MW, simple-cycle peaking powerplant uses 12 GE LM6000 SPRINT combustion turbine generators with evaporative cooling power augmentation to supply electricity to 500,000 homes via a 20-year power purchase agreement with Salt River Project.

At the push of a button during peak times, all 12 natural gas-fired turbines can start up in just 10 minutes—making this one of the largest plants in the U.S. capable of such a rapid start-up. With average ambient temperatures exceeding 100 degrees, the plant can continue to operate up to 122° F or as low as 15° F.

Safety was a key issue during the incessant summer heat. Construction work began at 3:00 a.m. and the workday ended before noon.

The original construction schedule called for the delivery of a turbine/generator and accessories every three to four weeks. But a major obstacle occurred when the truck transporting the second turbine to the site tipped over and the turbine was laid over on its side. The repair and re-delivery of the damaged turbine was going to take seven months.

Rather than focusing on the delays, the critical path construction schedule was revised and other available equipment was installed on site earlier than originally scheduled, keeping the crews working.

Detailed planning began at project award and continued throughout the execution of the project. Craft teams from laborers to foremen and superintendents had special planning sessions to improve repetitive work activities and find efficiencies in day-to-day tasks. Such careful planning and flexible management helped the project come in a month ahead of schedule and well under budget.

The judges appreciated the community partnering and social responsibility that the owner and contractor demonstrated to the region. For instance, TransCanada contributed $175,000 to a program to help keep young people in school by offering up to 10 scholarships annually to area high school students to attend Central Arizona College.

Keywords:

[ Page 1 of 2 ]
----- Advertising -----
Dodge Reports

Below is a brief listing of Projects Bidding in the South West. Click on any project to get Dodge Report, Plans and Specifications.

Click Here to See More Projects in the South West

Blog: From multiple ENR Southwest Bloggers
Our new blog delivers the latest project and people news, opinions and insights from the jobsite to the boardroom from the editors.
Reader Photos
Photos from Southwest Contractor Photo Showcase
Dodge Lead Center
FIND LOCAL
CONSTRUCTION PROJECTS
Search by Project Type & State



----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.