|
Great Heights
44 Monroe Rises Above Phoenix
By Scott Blair
The 34-story residential tower 44 Monroe rises above Phoenix
streets teeming with construction activity. Upon completion,
it will be the tallest residential property and the third
tallest building in Phoenix.
While Phoenix had made recent strides in developing its downtown
core by bringing in sports facilities, convention centers
and schools, it has lacked what many observers felt was essential
in forming a vibrant urban community: multistory residential.
The $75.6 million 44 Monroe tower will go a long way toward
changing that. Named for its address at First Avenue and Monroe
Street, the 34-story building will add 532,000 sq ft of residential
space to downtown Phoenix.
Upon completion in spring 2008, 44 Monroe will become the
tallest residential building in Arizona.
"The turnaround that's going on in Phoenix depends largely
on people actually staying here on nights and weekends,"
says Rick Fria, president of the Fria Co., a Carefree, Ariz.-based
project management firm representing Grace Communities, the
project's Scottsdale-based developer.
A
long-vacant 11-story office building stood at the small, quarter-block-sized
site. The developer had planned to turn this existing structure
into roughly 60 condominiums, but in order to maximize the
site's potential, the new 202-unit tower was chosen, Fria
says.
Demolition began in late 2005 and after the building was totally
removed, work on the foundation of 44 Monroe began in February
2006.
The foundation system consists of 52 caissons ranging from
5 to 8 ft in diameter and 55 to 80 ft deep; grade beams; and
an 85-ft-long, 64-ft-wide by 12-ft-deep concrete core foundation
mat, says Andrew Klem, project engineer with the Phoenix office
of the Weitz Co., the project's general contractor. The caissons
support the building above through friction with the surrounding
soil because bedrock was too deep.
"There are nine caissons located under the north basement
wall, which is actually a transfer beam/girder, as the columns
above are offset from the caissons below," Klem says.
"The remainder of the caissons directly support columns
or the foundation walls, and in some places both."
One level of parking is below-grade, while additional parking
will take up the second through seventh floors of the structure.
Rudy Erdmann, senior project manager with Weitz, says that
the most complicated part of the project has been the parking
levels. "There was so much steel [rebar] congestion,
especially in the heavier columns and slabs," he adds.
"The structural engineer, [Phoenix-based] PK Associates,
was onsite virtually full-time directing traffic and answering
questions."
Phoenix-based subcontractor Suntec Concrete used 6,000 psi
concrete for the floors and 10,000 psi for the columns. "With
the help of Wietz and Suntec, we developed a cost-effective
concrete tower structural system comprised of an 8-in.-thick
post-tensioned flat plate supported on 26-in.-square concrete
columns," says Cliff Paul, principal of PK Associates.
After starting out at a floor every 12 days, crews found their
rhythm and have been recently pouring a floor every week,
Erdmann says. The final floor was poured early this month.
"We need 34 concrete trucks per floor, and they cue all
the way around the block," he says. The trucks unload
two at a time into the concrete pump, which lifts it with
the aid of an auxiliary pump located on the floor that is
being poured. A swing-arm spout takes the concrete to its
final destination.
"It's a slick, organized system that has worked well,"
Erdmann adds. The condominium units range from 780 to 4,800
sq ft and range in price from $400,000 to $3.2 million penthouses.
The variety of sizes required four different floor plates
throughout the tower, each requiring adjustments in the concrete
forms.
Suntec devised a forming system specifically for the project,
Erdmann says.
"Instead of taking separate forms, erecting them, tying
them together and then pouring concrete, they did an entire
wall system of forms so that the entire wall could move,"
he adds. "You could put your rebar in, put the forms
back and then pour the concrete, all in one step, saving three
days per floor."
The tight urban site adjacent to major light-rail construction
prevented all but a miniscule area for staging. "The
key to staying on schedule on a job like this is managing
the vertical transportation, which includes the crane and
the man and material hoists," Fria says. "Material
has to come on an as-needed basis and it has to go right up
on the crane to where it's going to be used. Weitz has done
a good job of managing that."
The building's design initially included five metal fins that
started at the base and then continued up to the top and arched
over the top of the building, says Sharon Rissling, project
manager with San Diego-based Tucker Sadler Architects, who
were brought in to complete the job after the original architect
dropped off the project. "We subsequently had to cut
back some of that due to the high cost of product in the steel
especially," she says. The fins will now be formed with
metallic paint rather than metal to provide the building's
iconic look.
It was important to bring a well-tested and proven exterior
skin system in order to prevent water and acoustical intrusion
into the residences, Fria says.
"These two elements are usually where class-action litigation
in condos comes from, but it doesn't have to be that way,"
he says.
Glazing contractor Walters & Wolf's Phoenix office installed
a system designed by Concord, Ontario-based manufacturer Toro
Aluminum. "In our engineering and specifications we incorporate
the requirement to do field tests once it was installed on
site," Fria says.
During the test, 12 lbs of negative pressure are applied to
test portions of glass in specially sealed areas. "On
the outside we sprayed the entire one-story glass segment
with water and with that kind of negative pressure on the
backside, if there was a leak it would show up, guaranteed,"
Fria adds.
The first two of five tests were recently completed with no
leaks detected.
Key Players
GC: The Weitz Co.
Architect: Tucker Sadler Architects
Developer: Grace Communities
Owner Representative: The Fria Co.
Structural Engineer: PK Associates LLC
Subcontractors: Suntec Concrete; Wilson Electric; Tri-City
Mechanical; W.D. Manor Mechanical; Powers Steel & Wire;
Walters & Wolf; Arizona Partition
Click here for next Feature Story >>
|