|
Grand Canal
Scottsdale Ambitiously Develops Around Waterway
By David M. Brown
A variety of public and private projects are under way surrounding
the redesigned, 124-year-old Arizona Canal, which serves as
the lifeblood of downtown Scottsdale's revitalization.
A lot is going on along the Arizona Canal between Goldwater
Boulevard and just east of Camelback and Scottsdale roads
in downtown Scottsdale.
The final vision for the city-the only municipality in Arizona
where a canal runs through its downtown-is one in which the
central focal-point artery is not for vehicles but for pedestrians,
a water-centered area similar to San Antonio's Riverwalk.
Public projects along the 124-year-old canal include bridges,
a plaza, fountains, streetscaping and other canal-bank improvements.
On the private side are condominiums, lofts, mixed-use communities,
restaurants, boutique shops and office space.
Public Projects
A decade ago, anticipating development along the canal, Scottsdale
contracted with Salt River Project to construct vertical canal
walls between Goldwater Boulevard and Scottsdale Road, says
Jim Duncan, SRP's senior analyst for water engineering.
The walls structurally support cantilevered north-shore amphitheaters
as well as intensify the waterfront sensation for pedestrians.
In addition, to maintain a high water level, the city paid
for a radial gate structure at 64th Street, which controls
the elevation of water in the canal.
Scottsdale has since phased about $16 million in canal-bank
improvements.
The federal government has also pledged $400,000. Downtown
Reinvestment phase one was a $5.5 million contract including
the Marshall Way bridge, trolleyway, roundabout, bollards
(some retractable for trolleys and public-service vehicles)
and lighting.
Construction began in January 2003 and was completed in November
2005.
Downtown Reinvestment phases two, three and four comprise
$14.5 million in park-like improvements along the south bank
of the Arizona Canal between Goldwater Boulevard and Scottsdale
Road.
Downtown Reinvestment Phase 2
Phase two is a three-segment construction-manager-at-risk
contract with Phoenix-based W.E. O'Neil Construction Co. of
Arizona. The E-Group of Phoenix is the architect. Work began
November 2006 and is expected to be completed in December.
Marshall Way Plaza, phase 2a, is a $1.6 million contract,
which includes installing four fountains on Marshall Way on
the south side of the canal just over the bridge, courtyards,
landscaping and lighting. W.E. O'Neil is expected to complete
this project by August.
Stetson Streetscape, phase 2b, is a $750,000 project to complete
streetscaping as well as installing a storm drain on the south
side of the canal. W.E. O'Neil was awarded this project in
October and completed it in June, says Bill Peifer, senior
project manager with the city of Scottsdale.
The Southbank Park, phase 2c, is an approximately $1.6 million
contract expected to be awarded to W.E. O'Neil this month
to be completed by December. This job includes improvements
to the Maricopa County Sun Circle Trail along the south side
of the canal.
The trail connects county regional parks primarily by using
canal right-of-ways. Along the canal between Goldwater Boulevard
and Scottsdale Road, it will be marked by a 4-ft-wide granite
path and a 12-ft-wide concrete walk.
Phase 3, Northbank
Under a $1.7 million contract with Phoenix-based contractor
Opus West Corporation, construction included SRP right-of-way
roadwork from Marshall Way to Scottsdale Road and a cantilevered
amphitheater in front of the Waterfront Residences. Also part
of this was the creation of a spray water feature and other
landscaping by Floor Associates of Phoenix.
"The design concept draws heavily from desert landscape
imagery, incorporating the stylized forms of native cacti
and cactus flowers into the central water features, amphitheater
and hardscape plazas," says Chris Brown, principal of
Floor Associates. "Bold forms, colors and textures create
a unique sense of place, unifying the public and private areas
into a cohesive project."
This job was completed last month.
Phase Four, Goldwater Underpass
The Goldwater Underpass is an $800,000 project, split between
the city and the federal government, to connect a multiuse
path under Goldwater Boulevard on the south bank of the canal.
The city is expected to award the contract this month, Peifer
says. The project includes lighting, landscaping and increasing
the height of the existing underpass and connecting paths.
Soleri Bridge
Finally, the proposed Artist Waterfront Canal Bridge, designed
by Phoenix architect Paolo Soleri, would be the second pedestrian
bridge and plaza in the area, located just south of Camelback
Road on the west side of Scottsdale Road.
The city estimates approximately $4.3 million for the suspension
bridge, plaza, lighting, amenities, bell tower and extending
the Sun Circle Trail across Camelback and Scottsdale roads,
says Judith Patrylak, project manager for Scottsdale Public
Art.
The project is as yet underfunded, although Greenwich, Conn.-based
Starwood Capital Group, the co-developer of the Waterfront
condos on the north bank, has pledged $500,000 and the Scottsdale
Public Art program $1 million.
The Scottsdale City Council has asked the public art committee
to continue developing plans and will consider funding for
the fiscal year 2008/09 capital improvement program budget,
Peifer says. Adds city project manager Dan Worth: "If
the project is funded, we anticipate at least two years for
design and construction."
Future Public Projects
An additional canal-improvement phase would improve the Starwood
Capital Group-owned parcel west of Marshall Way to Goldwater
Boulevard, but the details of that project have not yet been
determined, although there is preliminary talk of a hotel
or condo/hotel, Peifer says.
In addition, a contract is expected to be awarded this month
to possibly reroute the waterfront sanitary sewer line. The
city has selected an engineering firm to analyze the situation
and propose solutions. No timeline for construction has been
set, but the city has designated $2 million for the project.
Private Projects
Three major developments are complete or in construction
along the canal banks.
Safari Drive Condominiums
Located at the canal east of Scottsdale Road, just north of
Camelback Road, the $55 million first phase of the Safari
Drive Condominiums got under way in May 2006.
The project is being built by Phoenix-based general contractor
Okland Construction Co. and Scottsdale-based developer Riverwalk
Development Co. and should be complete in December. Future
market-driven phases will include mixed-use residential, retail,
restaurant and office spaces, says Alan B. Collier, Okland
vice president and Safari project director.
Designed by Seattle-based Miller/Hull Design, the 191,000-sq-ft
condominium/mixed-used project includes an 80,000-sq-ft underground
parking structure. Owned by Scottsdale-based Vanguard CityHome,
which is managing the construction, Safari will include 96
units in phase one, from under 1,000 sq ft to more than 3,000
sq ft at a cost of $600,000 to more than $2 million.
The
basic construction is concrete, structural steel and metal
framing, and the exterior is Cor-Ten panels, stucco, floor-to-ceiling
glass, and glued-laminated roof structures, Colllier says.
"A significant challenge to the project has been incorporating
unique floor plates for the majority of the condominium units,"
he adds. The project's design called for various configurations
to make the final product more unique and appealing to buyers.
Collier adds that other issues included upgrading the city
and county storm drain in the Arizona Canal right-of-way and
integrating structural elements as finished surfaces.
Scottsdale Waterfront
The 1.1-million-sq-ft Scottsdale Waterfront mixed-use project,
nearing completion, includes retail and residential construction
components. The 11-acre project contains two residential towers,
office/retail/restaurant space and the yet-to-be-developed
acreage south of the Nordstrom's parking garage at neighboring
Scottsdale Fashion Square Mall.
Built by the Phoenix office of contractor The Weitz Co., the
two-level 202,000-sq-ft retail/office/restaurant component
was delivered to developers Starwood Capital Group and Golub/IDM
in July 2006.
This area extends from the southwest corner of Scottsdale
and Camelback roads to Marshall Way at the canal and includes
restaurants, boutiques, office condos and a 214,000-sq-ft,
double-level underground garage excavated by Phoenix-based
Buesing Corp.
Weitz constructed the parking garage with tilt-panel walls
and precast while the retail and office space was constructed
with structural steel components, says Melisa Johnson, project
manager with Weitz.
Phoenix-based Suntec Concrete and Coreslab Precast were the
concrete subcontractors.
In order to enhance the look of the project, stone, precast,
and EIFS were integrated throughout for individual facades.
Opus West Residential Development, an affiliate of Opus West
Corp., and Scottsdale's Geoffrey Edmunds developed the two
residential towers - a $240 million, 500,000-sq-ft project
on 2.25 acres.
The executive architect on the towers was Opus Architects
& Engineers, also an affiliate of Opus West Corp., and
the design architect was Chicago-based Solomon Cordwel Buenz
& Associates in association with Scottsdale-based H&S
International.
The 13-story towers offer 198 luxury condominiums, 1,100 to
5,000 sq ft, with an average sales price of $1.2 million.
OWR Construction, an affiliate of Opus West Corp., is the
general contractor for the towers.
The first tower, on the west end, has opened, and floors of
the second tower are opening in phases.
Crews had to deal with such issues as scheduling pours around
concrete shortages, maintaining adequate manpower and coordination
of deliveries and subcontractors on a tight site, according
to David Hullinger, director of construction with Opus West.
SouthBridge
The first phase of SouthBridge includes a four-building, 120,355-sq-ft
mixed-use project on a two-acre parcel at Stetson Drive, south
of the canal adjacent to the city's new plaza bridge. Allen
+ Philp Architects is the project architect, and W.E. O'Neil
is the general contractor.
The $30 million project consists of seven restaurants, retail
stores along the Stetson frontage and approximately 60,000
sq ft of office condos. It includes a two-level underground
parking garage with a spiral staircase to street level.
Developers Fred and Jennifer Unger, principals of Scottsdale-based
Spring Creek Development, which restored the Royal Palms Hotel
and Casitas in Phoenix and the Hermosa Inn in Paradise Valley,
say they wanted to create a one-of-a-kind urban village bringing
together non-nationalchain boutiques, shops, restaurants,
cultural festivals and art amidst a waterfront park environment.
To
achieve the look of an urban center grown over time, various
design aesthetics were used, including contemporary, early-20th
Century industrial, Mediterranean and a Spanish colonial interpretation,
says Jonathan F. Heilman, vice president for design with Allen
+ Philp. "The varied personalities of the buildings enhance
the retail concept of promoting locally-owned, independent
businesses with their own unique personalities."
W.E. O'Neil began construction August 2005, with completion
of phase one scheduled for this summer.
The second phase will include 24 condominiums east of Goldwater
Boulevard and fronting the south side of the Arizona Canal
and 42 condominiums fronting Fifth Avenue and the Arizona
Canal, west of Goldwater Boulevard, says Gary Roe, land-use
consultant to the developer.
Variously designed by Don Ziebell/OZ Architects, Allen + Philp
and Lamb Architects, all of Scottsdale, the units will range
up to 3,500-sq-ft brownstones facing the canal. The retail
component will occupy the ground floor fronting Fifth Avenue.
No contractor has yet been selected for the second-phase residential,
which will begin in six to 10 months.
Future Projects
The 24-year-old Kyoto Restaurant on Stetson Drive will be
replacing its existing building with a two-story canal-side
restaurant/office building of 15,000 sq ft with underground
parking. The project will complete the private-side projects
on the south bank of the Arizona Canal.
Selection of the general contractors has been reduced to two,
says Scottsdale architect Sam J. West, who adds that construction
of the approximately $4 million project will start when the
city issues the building permit.
Waterview @ Scottsdale will be a 10.37-acre mixed-use project
on the northwest corner of Buckboard and Camelback roads,
along the east side of the Arizona Canal. Its six buildings
will include an approximately 200-room luxury hotel, condos,
restaurants and office space, says John Wanninger, co-partner
with Mark Madkour of Scottsdale Canal Development.
Now in the design phase by Dallas, Texas-based Three Architects,
the project is still about a year from start, with a two-year
build-out.
Useful Sources
For more information on Scottsdale's canal improvement projects,
visit www.scottsdaleaz.gov/canal
For more information on the Soleri Bridge, visit
www.scottsdalepublicart.org/
development/waterfront.php
Click here for next Feature Story >>
|