|
All-In-One
Glendale Gets a New Hotel with a Whole Lot More
By Scott Blair
The new $112 million Renaissance Hotel, Glendale Conference
and Media Center is being built across the street from two new sports
arenas and a massive mixed-use development in Glendale.
|
The concept of fast track takes on new meaning with the new
Renaissance Hotel, Glendale Conference and Media Center located
in Glendale, Ariz. Portions of the project were required to
be completed before the Tostitos Fiesta Bowl which was held
January 1st, just eight months after the initial designs were
started.
The $112 million project consists of four different structures.
The 11-story Renaissance Hotel is being built by Springfield,
Mo.-based hotel developer John Q. Hammons Hotels. The city
of Glendale is concurrently building an 80,000-sq-ft conference
center, a 65,000-sq-ft media center and a four-level parking
structure.

The project owes its existence to the explosion of growth
in Glendale, including the University of Phoenix Stadium and
the Jobing.com Arena next door. The project is also bordered
by the mixed-use Westgate City Center.
The Renaissance will have the advantage of being the first
major hotel near the stadiums.
Major sporting events dictated the need for an early completion
date.
"The convention center, media center and parking garage
were done by December 1st," says Ronald Barrett, vice
president of operations for general contractor Killian Construction
Co., a Springfield, Mo.-based company that recently opened
permanent offices in Arizona. "It was about seven months
total construction, but that included design. It was seven
days a week, 24 hours a day, under very short time constraints."
The 320,000-sq-ft hotel required a longer construction schedule,
starting in January 2006 with a scheduled completion in September
2007.
The project is being delivered using the design-build method,
with a team including Hammons, the city of Glendale, Killian
and Springfield, Mo.-based architect Butler, Rosenbury &
Partners.
"We had to submit site and foundation drawings early
to get permitting so that the contractor could then begin
the process of building," says Douglas Jackson, AIA,
vice president at the architect's recently-opened Phoenix.
"While Killian was starting construction, we were completing
the final drawings for additional permitting so the contractor
could actually sub-bid out that work and order materials."
In order to produce drawings quickly, the architect at times
had more than 20 people working on the project. Meanwhile,
the contractor had up to 440 tradespeople onsite, Barrett
says.
While Glendale didn't allow any permitting or inspection corners
to be cut, the design-build team worked out a mutually beneficial
way to expedite the construction process. "The city actually
had offices here in the job trailer so that the inspectors
were on site every day just to make sure everything was going
as planned and as needed," Jackson says.
While separate structures, the hotel, conference and media
centers are connected on one side to allow hotel guests to
pass between them under one roof.
The convention center houses a 30,000-sq-ft main ballroom
and several smaller-sized rooms. The concrete foundation is
slab-on-grade while the structural steel frame provides clear
spans up to 125-ft-long.
The four-story media center will house production facilities
for Glendale's government-owned television station, Glendale
11, and for other media outlets during special events and
games. The building features a 30,000-sq-ft exposition area
and two production studios with green-screen walls, soundproofing,
extremely level floors and a low velocity mechanical system.
A 4,000-sq-ft press conference room is on the third level,
while the top floor houses an open-air viewing platform covered
by a semi-roof, for receptions and other media broadcasts.
"The whole facility is positioned so that when the Tostitos
Fiesta Bowl occurs, or when the Super Bowl is here next year,
the networks can come and just plug in," Jackson says.
The media and convention centers are equipped with over 100
floor boxes housing a variety of electrical currents, data
cabling and other connections to anticipate the technological
needs of media broadcasters.
The hotel tower is structural cast-in-place concrete, sitting
atop a concrete raft mat foundation, a floating 3-ft-thick
slab comprised of 4,600 cu yds of concrete.
"We used it because it was a faster and more economical
system to get the foundations moving on the hotel without
doing deep foundations, such as drilled or driven piers,"
Barrett says.
Due to the project's fast-track nature, some finish materials
in the original design were switched out during construction
due to availability.
"Some things you just can't get here fast enough,"
Barrett says. "A good example here was the use of a lot
of architectural pre-cast." The contractor minimized
its use from the original design and replaced it with Sedona
cut stone, which can be quarried in both Arizona and India.
"We saved the city about $400,000 on that one item,"
Barrett says.
A fast-track HVAC system technique provided another time-saving
strategy, he says. "We used a chill-pack unit, which
is like a mini-central plant all-in-one. It comes out of the
box already plumbed with pumps and chillers in place. You
just hook it up and it runs out chilled water to all your
systems and you are done."
While the hotel is not a resort destination, it does feature
several upscale amenities, including a spa, indoor and outdoor
swimming pools and a five-story atrium.
Key Players
Design-Build Team:
Killian Construction Co.; City of Glendale;
John Q. Hammons Hotels; Butler Rosenbury & Partners
Subcontractors:
Midwest Partitions; Miller Bonded; Cannon & Wendt;
Hardrock Concrete; Star Roofing; Riggs Contracting;
Coreslab Structures, Inc.; Schuff Steel Management; Traynor
Glass
Click here for next Feature Story >>
|