|
Bridge Over Troubled Waters
I-580, Galena Creek Bridge Finally Take Shape
by Tony Illia
The final segment of the $440 million I-580 extension between
Reno and Carson City is underway, including the construction
of a one-of-a-kind concrete arch bridge over Galena Creek.
|
Nevada's largest and toughest highway project is taking shape
after years of planning and design.
The $440-million, 8.5-mi Interstate 580 extension between
Reno and Carson City is now under way with a target completion
date of 2011. Fisher Sand & Gravel Co., a general contractor
based in Dickinson, N.D., was selected for the $393.3 million
project to complete the final segment. It's the biggest single
contract ever awarded by the Nevada Department of Transportation.
The new six-lane, 10-bridge freeway will bypass a busy, accident-prone
stretch of U.S. Highway 395 through Pleasant Valley that currently
sees 40,000 vehicles daily, making it Northern Nevada's most
congested rural highway. NDOT estimates there will be an 80%
increase in U.S. 395 traffic by 2015.
The new I-580 extension, designed by CH2M HILL Cos. of Englewood,
Colo., will help relieve that with more travel lanes, higher
speed limits and controlled-access on-and-off ramps. U.S.
395, by contrast, is an at-grade, four-lane highway with intersections
that don't have signals.
I-580, whose roots stretch back to 1957, will be a welcome
relief to local commuters. The freeway's first segment from
the Carson City/Washoe County line to Lakeview finished in
1964. It was followed by the Lakeview to Winters Ranch section
that opened in 1970.
But the Winters Ranch to Glendale Avenue portion ran into
trouble when project opponents filed lawsuits in 1972-73 challenging
the proposed alignment.
Congress, meanwhile, passed the National Environmental Policy
Act, which led to necessary environmental impact studies that
weren't completed until 1977. Additional segments came online
in the 1980s and early 90s, carrying the freeway to Virginia
Street and the Mount Rose Highway.
Strong public interest in the new freeway extension led to
nine months of meetings with the neighbors and local advisory
boards, producing an environmentally sensitive, low-profile
design. The alignment, as a result, connects at the Mount
Rose interchange and travels southwest along the hillside
to join the existing freeway at the Bowers Mansion cutoff.
Although aesthetically pleasing, the alignment is located
along steep and rocky terrain, which has brought numerous
engineering challenges, including a 1,722-ft-long, 300-ft-tall
bridge spanning Galena Creek about 20 mi south of Reno.
"It will be the nation's longest cathedral-arch bridge
once it's completed," says Scott Magruder, NDOT spokesman.
"It's a one-of-a-kind structure."
The project has faced other challenges. NDOT parted ways with
contractor Edward Kraemer & Sons Inc., three years into
construction. The Plain, Wis.-based firm was awarded a $79.5
million contract in November 2003. But the two parties mutually
ended their working relationship in May 2006 over a disagreement
on the Galena Creek Bridge's pilot truss erection.
Kraemer was paid 58.6% of its contract at the time of its
departure, leaving the span about 40% complete. It had also
nearly finished three smaller approach bridges. NDOT repackaged
the remaining work with 8.5 mi worth of divided freeway paving
and miscellaneous retaining walls, storm drainage and lighting.
In November, NDOT awarded Fisher Sand & Gravel the low-bid
contract, even though the firm's bid was 19.1% over the engineer's
estimate.
"We needed to award this project because construction
inflation will probably be 14 to 16% in 2007," says NDOT
Director Susan Martinovich. "But we're going to cut our
pavement preservation program by 50% to help pay for it."
Fisher partnered with C.C. Myers Inc. of Rancho Cordova, Calif.,
to tackle the project's 10 bridges, which make up about 31%
of the workload.
The majority of bridges are all cast-in-place, post-tensioned
box girder structures, says Bill Crawford, CH2M HILL's senior
transportation technologist. The Galena Creek Bridge, however,
consists of two parallel three-lane concrete-and-steel structures
with 689-ft main spans.
The pilot truss erection method, designed by NDOT, calls for
18 steel segments to be bolted and welded together, forming
a structural framework.
The contractor then wraps rebar and concrete around the trusses
to produce a finished bridge.
But Fisher wants to fill the canyon with 300,000 cu meters
of compacted soil, temporarily raising the creek floor by
140 ft, and erect conventional falsework. (The proposal is
still pending NDOT approval.) The project requires hauling
a total of 3 million cu meters of earth. Fisher will excavate,
haul and grade the material itself.
"At any given time, we'll be running 40-plus machines,"
says Tommy Fisher, company president. "We're producing
all the aggregates from the excavation so it allows us to
be self-sufficient."
Fisher will have crushing and screening operations at each
end of the project, with central batch and hot plants. The
firm will self-perform the asphalt paving, which is 90% of
the roadway, and subcontract the remaining concrete component
to McNeil Bros. Inc. of Phoenix. The project will use 900,000
tons of aggregate base, 1 million tons of backfill and 3,000
tons of hot-mix.
"We'll have 200 people onsite at the peak of construction
activity," Fisher says. "Our vertical integration
enables us to do almost everything onsite, eliminating worries
about trucks getting struck in traffic."
The 1,000-day project schedule, which carries $12,700 a day
in liquidated damages for late completion, is currently on
track to finish in 2011. <<
Key Players
Owner: Nevada Dept. of Transportation
General Contractor: Fisher Sand & Gravel
Consulting Engineer: CH2M HILL
Bridge Contractor: C.C. Myers Inc.
Other: Case Pacific Co.; Rinker Materials; Par Electrical
Contractors Inc.; McNeil Bros. Inc.
Click here for Next Feature Story>>
|