|
Las Vegas Airports Take Flight
McCarran Expands While New Ivanpah Airport Lifts Off
By Tony Illia
McCarran Airport is preparing for Las Vegas' ever-growing
influx of visitors by opening a new consolidated rental car
facility, expanding two existing gates and adding a new terminal.
Meanwhile, the $4-billion new airport planned for the Ivanpah
Valley moves forward.
|
McCarran International Airport, the nation's fifth busiest,
is undertaking a five-year, $3.8-billion capital improvement
program to meet the rapid growth of the Las Vegas Valley.
San Francisco-based Bechtel Infrastructure Corp. is the program
manager.
McCarran handled nearly 46.2 milllion passengers in 2006,
and for every new hotel room added to the city's inventory,
another 320 passengers come through McCarran, says Randall
H. Walker, director of the Clark County Dept. of Aviation.
Currently there are 36,725 more hotel rooms planned through
2010, a 27.6% increase over last year's inventory, reports
the Las Vegas Convention and Visitors Authority. The 2,800-acre,
four-runway airport could consequently soon reach its 53-million
passenger capacity. McCarran trails only LAX as the nation's
busiest origin and destination airport with more than 121,000
passengers daily, Walker says.
McCarran is undertaking a series of capacity expansions and
facility upgrades to meet demand, while pursuing the construction
of a new airport in the Ivanpah Valley, 40 miles southwest
of Las Vegas.
Ivanpah Airport
The Ivanpah airport will be located on a dry lakebed east
of Interstate-15, between Jean, Nev., and the California border.
A $14.2 million environmental impact statement for the new
6,000-acre airport complex is being prepared by Watertown,
Mass.-based Vanasse Hangen Brustlin. The initial $4 billion
phase will consist of a 14-gate terminal with two parallel
runways for concurrent takeoff and landings, with 2,000 acres
allocated for flood control.
It is expected to be operational by 2017, servicing six million
passengers in its first year. McCarran will eventually shift
its focus to short-commuter flights, with Ivanpah assuming
the long-distance and international routes.
"This will be the first new major airport in the country
since Denver," says Jonathan Feinstein, VHB senior vice
president, whose firm won the contract as a result of a national,
three-stage competition. "In addition to the airport
there will be 14,000 acres of land for commercial and industrial
development."
The Southern Nevada Public Lands Act of 1998 created a 200-ft-wide
utility corridor from Las Vegas to Ivanpah, helping fast-track
easements over federal land for bringing water and electrical
power to the site.
The final environmental report has to be submitted by 2010
for federal approval. If cleared for takeoff, design will
take three years followed by four years of construction. The
county has retained URS as their aviation consultant.
Construction of the Ivanpah facility will be financed from
federal grants and revenue bonds, with debt being retired
from passenger fees, concessions and airport revenue. Upon
build-out, it will service up to a 35-million passengers annually.
Rent-A-Car Center
McCarran, meanwhile, is freeing up space at its existing facility
by moving car rental operations offsite to a new 79.2-acre
complex at Gilespie Street and Warm Springs Road. Check-in
counters inside the terminal building will be converted into
added baggage carousels.
The $123.3 million Rent-A-Car Center will consist of a three-level,
1.7 million-sq-ft garage capable of storing 6,000 cars. The
cast-in-place concrete structure will have an 11-acre footprint.
Denver-based PCL Construction is the general contractor.
The project also entails a two-story, 131,000-sq-ft customer
service building, designed by Las Vegas-based SH Architecture.
The steel-framed, crescent-shaped structure will house 10
rental car companies capable of conducting 10,000 transactions
daily. The building will feature a concrete block and sandstone
veneer, with glass and aluminum panels.
"We tried to make the orientation as direct and simple
as possible for new visitors," says John Sawdon, principal
of SH Architecture.
Other project components include three quick turnaround areas
with fuel and service islands as well as two-story light maintenance
facilities. There will be a total of 125 gas pumps with 150,000
gallons of fuel available in underground tanks that will need
refilling every two days. It will be the largest gas station
west of the Mississippi, claim project officials. >>
Car companies signed a 10-year lease to occupy space inside
the new Rent-A-Car Center, which is scheduled to open this
month. A $3-per-transaction service charge will help underwrite
passenger shuttles. McCarran will run 60 buses in a 2.3-mi
loop between the airport and back. It expects to receive about
$20-million annually in car rental revenue.
Terminal 3
McCarran's consolidation of its car rental operations allows
it to build a new 1.87 million-sq-ft third terminal building.
The $1.8 billion, 14-gate Terminal 3, located north of the
D-Gates, will be totally self-contained with its own security
gates, baggage claim, retail concessions, parking and ticketing,
says Elaine Sanchez, McCarran's public information manager.
The project, which will have six gates dedicated for international
travelers, is scheduled to reach 100% design completion next
month. Las Vegas-based PGAL is the architect. Terminal 3 will
give McCarran 117 total gates -- its final build-out capacity.
The project is tentatively scheduled to open by 2011.
Construction, however, requires a $55 million realignment
of Russell Road, between Paradise Road and Eastern Avenue,
to the north. McCarran had previously purchased 440 surrounding
homes to make room for the realignment, which is expected
to finish mid-year. Terminal 3 will connect to the D-Gates
via a concrete reinforced underground tunnel for an Automated
Transit System.
D Gates addition
The D Gates are undergoing a $109-million, 128,000-sq-ft expansion
with St. Louis-based McCarthy Building Cos. as general contractor.
The 9-gate northwest wing addition, designed by Henderson-based
Tate Snyder Kimsey Architects, will consist of a two-story,
steel-framed structure set atop spread footings. The 500-ft-long
fan-shaped structure will feature a combination glass curtain
wall facade with sunshade louvers, and aluminum and zinc metal
paneling. It will also have exposed bowtie roof trusses, clerestory
windows and 80-ft-tall central pyramid-shaped atrium that
allows indirect sunlight to filter down.
The lower level will house mechanical, electrical, security,
luggage and other back-of-house services, while the main level
will have ticketing, passenger lounges and 10 retail spaces.
The 36 month project will require 16,000 sq ft of glass and
1,600 tons of steel.
"There are some restrictive work hours during the holidays,
but the job generally requires a lot of coordination between
the subs, the owner, the construction manager and tenants,"
says Randy Highland, McCarthy's Nevada division president.
"We are also working around take-off and landings, which
entails some security restrictions."
The northwest wing is expected to finish by September 2008,
employing up to 250 trades during the height of construction
activity. It will give the satellite terminal 44 total gates
upon completion.
C Gates security checkpoint
McCarran could reach capacity five years before the new Ivanpah
Airport opens. As a result, officials are looking to upgrade
existing operations where possible.
For example, the airport is spending $65.4 million to build
a new pedestrian link between the C and B gates as well as
a new security annex. Las Vegas-based Flagship Construction
Co. LLC is the general contractor. The 64- ft-long, 35-ft-wide
and 17-ft-high elevated skybridge is an enclosed steel-and-glass
structure with moving walkways and retail areas. The two-level,
65,000-sq-ft security screening building has security and
ticketing check points, offices, concession areas on the second
level, with storage, mechanical and airline spaces underneath.
Domingo Cambiero Corp., Las Vegas, is the architect.
"Bringing additional passengers through our airport takes
more than just adding flights," says Walker. "We
must have the terminal facilities in place to handle passengers'
needs, and roadways to facilitate the safe and efficient movement
of private and commercial vehicles."
Key Players
Construction Manager: Bechtel Infrastructure Corp.
Contractors: Flagship
Construction Co.; McCarthy Building Cos.;
PCL Constructors
Architects: Tate Snyder
Kimsey Architects; SH Architecture;
PGAL; Domingo Cambiero Corp.
Engineers: Vanasse Hangen
Brustlin; URS
Click here for Next Feature Story >>
|