|
Ready for a Close-up
Albuquerque Studios Ushers in New Era of NM Film
By Scott Blair
New Mexico's film industry entered a new era in January with
the
opening of the first phase of Albuquerque Studios, a $74 million
movie studio at Mesa del Sol.
|
Developed by Albuquerque-based Union Development Corp., the
project was ushered into reality with an aggressive incentive
program from the state's economic development office.
"It was one of the best incentive programs ever initiated
for the film industry and all of the parties funding the project
were extremely excited about the possibility of building an
industry here," says Nick Smerigan, chief operating officer
of Albuquerque Studios. "We believe both the state and
local governments are very interested in building an industry,
rather than a situation that would come and go like it does
in Canada."
Once the site was identified and financing secured, developers
wanted the studio opened as soon as possible, which led to
an extremely tight timeline.
"We needed to go through two different city approvals
on entitlements and then get our building permit, and we did
it on a piece of property that was not zoned correctly, or
platted or subdivided," says Jim Trump, president of
Union Development Co. "The City of Albuquerque and Mayor
Chavez's efforts were unbelievable to help us meet our construction
schedule."
The project wasn't officially design build, but the construction
team, including Albuquerque-based architect Dekker/Perich/Sabatini
and contractor Jaynes Structures, used many of the same techniques.
"We worked with Jaynes from the very beginning as far
as scheduling and budget issues because it was such a short
time frame," said Christopher Gunning, AIA, with Dekker/Perich/Sabatini.
"They ended up ordering their steel before we hardly
had the building designed."
Other long-lead items were ordered before the July construction
start date.
"Even before we were closed on the property, they suggested
we purchase concrete and steel because those prices were going
to go up," Smerigan says.
"That's what's allowed us to move forward at such a rapid
rate."
Phase one included four buildings: Two large 76,000-sq-ft
buildings will contain two 24,000-sq-ft stages each, plus
25,000 sq ft of office space. The third building contains
two 18,000-sq-ft stages and 22,500 sq ft of office space.
The fourth structure houses a 78,000-sq-ft warehouse space
to store sets and an 8,000 sq ft central chiller plant. However,
each stage has its own electrical system. "We have 6,400
amps of three-phase power on the stages so that they can support
the lighting equipment that is necessary to do filming,"
Smerigan says.
Albuquerque-based McDade Woodcock was the electrical contractor
on the project.
The stages feature slab-on-grade foundations and are comprised
of tilt-up concrete panels. The office portion uses a structural
steel frame.
"The concrete panels are, from what we understand, the
largest that have ever been placed in New Mexico," says
Barry Tulk, preconstruction manager and estimator with Jaynes.
The largest panel was slightly over 75 ft-tall, 20 ft-wide
and 11.5 in.-thick, the large size dictated by the need for
55-ft clear heights in the finished studios for maximum flexibility
in set design.
"One of the biggest factors was making sure there was
a crane available in the right time period," Tulk adds.
A 300-ton crawler crane was used for raising the 110-ton panels.
Over 13,600 cu yds of concrete was used on the project. "We
started numerous pours at 2 a.m. just so we could get the
amount of trucks needed per day to meet our schedule,"
Tulk says. The site was only accessible by one road at the
time of construction, so daytime traffic woes made the night
pours essential.
Steel trusses span up to 180 ft to support the 4-in. concrete
deck roof and rigging systems to hang lights and sets from.
"We bowed the top of the trusses, mostly because a lot
of the older movie studios in Califonia have those old bow-string
trusses," Gunning says. "We thought it would be
cool to recognize that some of the form of this building is
evocative of those historic studios."
The project's steel subcontractors were Bernalillo, N.M.-based
AmFab Inc. and Lubbock,Texas-based W & W Steel.
An exhaust system was installed in each studio to handle any
smoke or other fumes caused by stunts during filming. "It
has to be exhausted in a reasonable amount of time, which
for us is 25 minutes to totally change the air in the 24,000-sq-ft
space," Smerigan says.
The next phase at the studio is already being planned. "We
are pricing two more 18,000-sq-ft stages, and two 100,000-sq-ft,
four-story office buildings," Trump says.
In addition, Smerigan says he has had several discussions
with the University of New Mexico about a possible film school
at the site.
Key Players
Developer: Union Development Co
Owner: Pacifica Ventures
Architect: Dekker/Perich/Sabatini
General Contractor: Jaynes
Structures
Electrical: McDade Woodcock
Mechanical: Yearout Mechanical
Steel: AmFab; W & W Steel
Other: Western States
Fire Protection; Franklin's Earthmoving
Click here for Next Feature Story >>
|