|
Special Delivery
St. Joseph's Expands with Women's Pavilion
By Richard Kim Folsom
Carondelet St. Joseph's Hospital opened in 1961 on the growing
east side of Tucson. This growth continues today, so Carondelet
has embarked on a four-phase expansion of the hospital. Phase
one adds a women's health pavilion, parking garage, medical
office building and updates to the mechanical plant.
|
Carondelet Health Network's $40 million phase one expansion
of St. Joseph's Hospital on its 55-acre facility in Tucson
is a project of partnerships.
"Carondelet was so supportive of the partnership concept
on the project," says Fred Briscoe, the project manager
for Phoenix-based Sundt Construction, the general contractor
on the project in a joint venture partnership with Tucson-based
BFL Construction. "Carondelet promoted input from all
members of the construction team, their staff and the surrounding
community to achieve the best design."
The partnership continued with the architectural team, comprised
of Nashville, Tenn.-based Gresham Smith & Partners and
Tucson-based Swain Associates. "Because of the strict
codes on healthcare design and construction, cooperation and
coordination did not stop with the construction team,"
says Mark Bollard, AIA of Swain Associates. "The city
of Tucson was very flexible in permitting the hospital construction.
The city allowed phased permitting which covered basic excavation
and prep work without having to get a permit for the whole
construction project."
M. Channing McLeod, AIA, the project architect for Gresham
Smith says that the design's main objective was to create
a pleasant and safe environment.
"The patient rooms, operating and delivery rooms were
all designed repetitively so every feature in every room was
exactly in the same place," McLeod says. "This 'patient
safe design' is a little more costly up-front but reduces
staff mistakes once the facility is in use, saving much more
financially for Carondelet."
The site currently houses the existing hospital, a medical
office building and parking, with the expansion planned for
four separate phases. Phase one includes a Women's Medical
Pavilion that will add approximately 164,000 sq ft and will
be connected on two floors to the existing hospital. The five-story
pavilion, scheduled for completion in July, will include labor
delivery rooms, a natal intensive care unit, pre-natal special
care and isolation rooms. The fifth floor will be devoted
to neuroscience.
The other three phases will be started in the next couple
of years, according to the project master plan. A cost for
the overall expansion has not been determined, and contracts
for the other phases have not yet been awarded, according
to Bollard. However, Swain is also designing a medical office
building on the site under a separate contract.
The construction team worked diligently to plan ahead. "The
team, with the owner's blessing, bought materials ahead of
time to avoid cost increases in material during a volatile
construction products market," says Briscoe. For example,
Michael Crane of Sturgeon Electric in Denver, which has an
office in Tucson, worked with Stark Electric of Tucson and
purchased most of the electric wire ahead of time. "The
total value of the wire on this project was $560,000 when
purchased in November, but value has increased about 40% since
it was purchased," says Crane.
"Sundt also pre-purchased 5000 cu yds of concrete that
was used for the Pavilion foundation and elevator shaft for
the same reason," says Briscoe.
Phoenix-based Able Steel pre-purchased 960 tons of steel for
the building's structural steel frame early in the project
to take advantage of lower materials pricing, according to
the steel contractor's project manager, Mike Adamowicz. "One
problem the contractors and subs had to deal with because
of pre-purchasing was onsite storage. The steel had to be
unloaded from trucks and immediately erected, leaving no room
for error."
Meanwhile, Robert Lee of R. E. Lee Mechanical Contracting
Inc. of Tucson worked to make sure that the construction went
ahead as scheduled without interruption to any existing hospital
services, especially when it was determined that the sewer
and ventilation systems needed to be modified.
"The work had to be completed within a two week period
so that the adjacent hospital would not be impacted,"
says Lee. "Special carbon filters were added to the outside
air intakes with a less expensive removable pre-filter so
that patients would not be irritated by odors from the construction."
The sewer system was re-routed and three ejection basins with
pumps were added.
Time was also essential in the power plant upgrade, according
to Lee. Two of the existing generators had to be replaced
with larger units. The work had to be done in the wintertime
during the middle of the night when power usage was at the
lowest level in the hospital. This doubled the emergency generation
capacity and increased normal power by about one third.
Tucson's wet monsoon season last year became an issue at the
site when rain water filled a new elevator shaft, according
to Briscoe. Since environmental regulations prevented the
water from being removed from the site, crews ended up moving
the water around on the site as they worked on the project.
Key Players
Owner: Carondelet Health
Network
Architect: Gresham Smith
& Partners; Swain Associates
General Contractor: Sundt/BFL
Construction
Engineer: Grenier Engineering
Electrical: Sturgeon Electric;
Stark Electric
Mechanical: R E Lee Mechanical
Contracting Inc.
Steel: Able Steel
Useful Sources
St. Joseph's construction website:
www.carondelet.org/csjconstruction/
Click
here for Next Feature Story >>
|