|
From Trash to Treasure
Brownfield Site in Tempe Flowers into Upscale Retail
by Scott Blair
Rising from a former brownfield site along the Salt River
at Rio Salado Parkway and McClintock Drive in the Phoenix
metropolitan area's East Valley, Tempe Marketplace is taking
shape on land that had once been occupied by landfills and
industrial-type businesses. .
The $250 million, open-air destination for shopping, dining
and entertainment now under construction will provide 1.3
million sq. ft. of retail space with special features such
as elevated fireplaces, outdoor gathering spaces and even
a laser light show.
The project, being developed by Phoenix-based Vestar Development
Co., is expected to open by Summer 2007.
The project is divided up into two main components: The District
at Tempe Marketplace is a 380,000-sq.-ft. open-mall style
center which is directly inspired by Vestar's earlier successful
retail project, The District at Desert Ridge Marketplace in
north Phoenix. McCarthy Building Cos. of Tempe was the general
contractor on Desert Ridge and has again been tapped for this
project.
The other component, known as the 'in-line majors', is comprised
of medium-sized big-box stores such as Ross, Cost Plus and
Pier 1 Imports, forming an exterior ring around the centralized
District. The Phoenix office of Adolfson & Peterson Construction
is the general contractor for this phase. Additionally, the
contractor is constructing several other big-box retail buildings
at the site outside of their contract with Vestar, including
a Target and Sam's Club.
Yet another general contractor, Scottsdale-based Double AA
Builders, has been retained to construct a 16-plex Harkins
Theatre at the east end of the District.
Having multiple contractors and all their subcontractors on
the 117-acre site concurrently adds to the complexity. "There
are so many contractors on site trying to get into certain
areas at the same time," said Ken Foudy, project manager
with Adolfson & Peterson. "There are quite a few
meetings and a lot of coordination to make it happen."
The site was assembled by Vestar from up to 80 individual
parcels of land and over 50 landowners. "This is definitely
not a typical deal for us in the state of Arizona," said
David Malin, Vestar's project manager. "Most of our projects
in Arizona are in growth areas, and we are usually dealing
with one owner."
Instead, Tempe Marketplace is an infill project in an already
mature market.
"It was one of the most complicated land deals ever done
in the state of Arizona," Malin added.
The site was formerly a county island between valley cities
until annexed by Tempe in 1999 where businesses were not heavily
regulated.
"We've run into just about everything you can possibly
run into on a site," said Rob Kerwin, managing partner
with Foursite Consulting, the project manager for Vestar on
the project. "The remediation was a project in itself.
Prior to having acquired all the parcels, we were doing remediation
on the ones that we had acquired while still negotiating the
acquisition of the remaining parcels."
During remediation methane, lead and PCB contamination was
found, and a variety of undocumented landfills were either
stabilized or in some cases removed entirely, according to
Kerwin. One large landfill that fell directly under a planned
building footprint required excavation and removal of 130,000
cu. yds. of earth.
With other non-organic dump sites, the soil was either screened
or was kept in place and put through a deep dynamic compaction
process. "We took a 28.5-ton weight and raised it up
to a height of 85-ft. on a special crane fitted for this type
of work," Kerwin said. "Then we dropped the weight
a number of times in a very precise pattern." Santa Paula,
Calif.-based Hayward Baker Inc. performed the compaction,
with the Phoenix office of Brown and Caldwell acting as environmental
consultant.
Construction on the buildings began in July 2006. Design of
the project was handled by Phoenix-based Butler Design Group,
which has collaborated with Vestar on six other major retail
projects over the past five years.
The District features 11 separate masonry structures built
on concrete slab foundations, while the in-line majors are
comprised of pre-cast concrete panels cast on-site.
Some remediation is still being performed. "We've been
doing a lot of jumping around and adjusting the sequence accordingly,
so having the 11 buildings adds to that flexibility,"
said Jim Brandt, project director with McCarthy.
Due to the large amount of masonry work on the District, McCarthy
chose to bring in two masonry contractors, Mesa, Ariz.-based
Rhino Masonry and Glendale, Ariz.-based Maverick Masonry.
"We thought that it was a big enough scope of work and
an aggressive enough schedule to have one subcontractor working
on the east half while another masonry contractor works on
the west side, both at the same time." >>
Over 250,000 masonry units will be used upon completion of
the District, and the outdoor walkways will feature 200,000
sq. ft. of colored hardscape pavers in varying patterns, according
to Brandt. Abundant metal panels and canopies, five different
water features and exterior finishes of stucco and plaster
will add visual interest to the completed project.
Coordinating the needs of up to 100 separate retail tenants
has been a major component to the project. "You have
to make sure you are meeting the needs of all the tenants,
so that everything with the core and shell is taken care of
before they come in and start doing the build-out of their
interiors," Brandt said.
"What makes retail a different animal is the complexity
-- not so much from the type of construction that we do, which
is fairly straightforward -- but in the sense of the intense
degree of coordination required with the various tenants,"
Kerwin said.
Key Players
Developer Vestar
Development Co.
Architect: Butler Design Group
Construction Manager Foursite
Consulting
General Contractors: McCarthy
Building Cos.; Adolfson & Peterson;
Double AA Builders
Environmental Consultant: Brown
& Caldwell
Subcontractors: Suntec
Concrete; Rhino Masonry; Maverick Masonry; Schuff
Steel; Corbins Electric; JEN Electric; Baker Concrete; Universal
Piping LLC
Click
here for Next Feature Story >>
|