Taking a Bite out of Crime
New Crime Lab for Phoenix
by Scott Blair
Though the new Phoenix Forensic Crime Laboratory broke ground
in July of 2005, the lab's design and construction documents
were being finalized during some of the largest cost increases
for materials the building required the most: steel, concrete,
copper and petroleum products.
"We pretty much got hit with everything," said
Nancy Crump, assistant crime lab administrator with the City
of Phoenix Police Department. "We've had to evaluate
the budget at every step in the process, as well as do a lot
of value engineering."
Providence, R.I.-based Gilbane Building Company was brought
in early through Phoenix's new construction manager at risk
process which is required on all city-funded projects. "We
had approximately $1.5 million of value engineering that was
accepted on the project," said Todd McMillen, project
manager with the contractor. "The original concept of
the flooring was terrazzo, which is very high-end. Lab settings
such as this typically react better to vinyl-type flooring."
Sheet vinyl with welded seams was chosen as the primary flooring,
saving approximately $400 thousand.
The $34.6 million project is currently 50 percent complete,
and nearly three months ahead of schedule. Completion is anticipated
by June of next year.
With three levels situated in an 'L' shape at the intersection
of 7th Avenue and Jefferson Street, the 104,000-sq.-ft. lab
will give the department more than five times their existing
space. Lab space is housed on one wing, while office space
occupies the other.
Height restrictions relating to the site's proximity to the
Sandra Day O'Connor Federal Courthouse required the three-story
structure to have the first floor completely below-grade.
"It did allow us to get our program size into a smaller
footprint and leave more of the site open for planting and
trees," said Evan Sockalosky, designer of the project
with the Phoenix office of architectural firm Durrant. >>
The green area will sit above a two-level underground parking
structure comprised of pre-cast concrete. "Having a park-like
setting on top of a parking structure creates a challenge
with the size of trees and the amount you can get, and still
drain the plaza in the correct way," Sockalosky said.
The laboratory building is comprised of structural steel
on spread footings with a slab-on-metal deck for the upper
two stories. A mechanical penthouse houses the building's
ample mechanical requirements, including air handler units,
exhaust fans and boilers. A separate cooling tower is located
on the southwest corner of the building.
"The lab exhaust system is a very critical requirement,"
McMillen said. "There are in the order of 50 combined
fume hoods and bio-safety cabinets with very specific control
and exhaust systems." The cabinets will use venturi valves,
which are digitally-controlled, cone-shaped air valves with
almost immediate response time.
The shape of the building is a result of the building's mechanical
requirements. Since the labs needed single-pass air with 100
percent exhaust, creating two separate wings allowed for a
more efficient layout of the mechanical systems, according
to Sockalosky.
Another benefit to the shape was controlling the flow of
evidence through the building. Evidence will be brought in
through a secure vehicle checkpoint located on the lower level
of the facility and placed into secure lockers. From there,
'wet' evidence that may contain bodily fluids is brought to
a drying room with separate entry and exit points to avoid
any introduction of contaminants.
Examination facilities include laboratories for photo analysis,
latent prints, DNA testing, toxicology, controlled substances
and forensics.
A firearm testing lab features a firing range for cartridge
ejection and recovery analysis, and features sound attenuation
and high air flow due to toxic lead released from the bullets.
There are also three vehicle examination bays in the lower
level.
"As common with most crime labs, we have backlogs and
limited resources," Crump said. "Moving into this
new building should allow us to really attack that backlog
once we are fully staffed. It's going to be infinitely better
than what we are used to working in right now."
In May, the city granted a five-day road closure of one of
Phoenix's busiest streets, 7th Avenue, to Gilbane so that
the contractor could position a large crane and multiple tractor
trailers in order to erect the exterior pre-cast concrete
panels onto the building's west face.
Gilbane coordinated their subcontractors to be on the site
24 hours a day in staggered, back-to-back shifts. Each trade
would hand off their work zone from one trade to the next
as they completed their portion of the job. Phoenix-based
Coreslab Structures was the concrete contractor while Buesing
Corporation handled excavation. Other trades involved in the
activity were barricade contractor Jones Concrete Construction,
underground utility contractor Juarez Contracting and Progressive
Roofing, all of Phoenix.
The erection was completed and the roadway re-opened 24 hours
ahead of schedule. "It was a flawless orchestration of
construction activities that were continuous during the entire
96 hours and completed safely," McMillen said.
|
Key Players
|
| Owner: |
City of Phoenix Police
Department |
| Architect: |
Durrant |
| Structural Engineer:
|
KPFF Consulting Engineers |
| CM at Risk: |
Gilbane Building Company |
| Electrical: |
Rosendin Electric |
| Mechanical: |
Bel-Aire Mechanical |
| Steel: |
Schuff Steel |
| Excavation: |
Coreslab Structures;
Jones Concrete Construction |
| Excavation/ Shoring:
|
Buesing Corp. |
|