1.Semiconductor Fab Plant
#32 Estimated Cost: $3 billion Started:
August 2005 Target Completion: August 2007 Owner: Intel Corp Architect:
IDC General Contractor: Hoffman Construction Company
Intel Corp.'s
new one million-sq.-ft. wafer chip manufacturing facility will occupy a 131-acre
site in Chandler. The 60-ft-tall building is a combination of steel-frame and
concrete pre-cast tilt-wall construction with a glass, masonry, and metal panel
skin. The structure is supported by over 800 concrete columns, with shear walls
and structural steel brace frames. The eight-level building, two of which are
below grade, will become Santa Clara, Calif.-based Intel's sixth 300-mm wafer
facility. It's expected to create up to 1,000 new jobs and a $2.6-billion annual
economic impact.
|
2.
Metro Light Rail: Line Sections 1-5 & Town Lake Bridge Construction
Cost: $343.2 million Started: January 2005
Target Completion: 2008 Owner: Valley Metro Rail, Inc. Design: Parsons
Brinckerhoff; Gannett Fleming; URS Corporation; AZTEC Engineering; David
Evans & Associates; Stantec; Jacobs Engineering; HDR; TY Lin International
General Contractors: Kiewit Western (Line 1); Herzog Contracting (Line 2); Archer
Western Contractors (Line 3); Sundt/Stacy & Witbeck, a joint venture (Lines 4/5);
PCL Civil Constructors, Inc. (Bridge)
The five line sections and
bridge over Tempe's Town Lake that comprise the first phase of the Valley's Light
Rail project encompasses 20-mi. of track stretching from north Phoenix to west
Mesa. Construction activity includes: utility relocation; demolition and reconstruction
of streets, curbs, sidewalks and streetscapes; pouring the concrete foundations
for the embedded rail track, 27 stations and hundreds of overhead power system
posts; and laying the track. The 1,531-ft. long bridge features 11 piers and 42
steel trusses up to 160-ft. long. 3. Scottsdale
Waterfront Construction Cost: $200 million Started:
Late 2004 (Retail/Office); February 2005 (Residential) Target Completion:
December 2006 Owner: Scottsdale Waterfront LLC; Waterfront Residences, LLC
Architect: Solomon Cordwell Buenz & Asssociates/ H&S International/ Nelsen
Architects (Retail/Office); Opus Architects & Engineers (Residential) General
Contractor: The Weitz Co. (Office/Retail); Opus West Construction Corp. (Residential)
Engineers: Brooks Engineers & Surveyors, Inc.; Solomon Cordwell Buenz
& Associates Electrical: Wilson Electric; JEN Electric Mechanical: Tri-City
Mechanical; HACI Mechanical Contractors Concrete: Sundt Construction, Inc.;
Coreslab Structures, Inc. Steel: TW Steel Corp.; Dunn del Re Steel Co. Inc.
The Scottsdale Waterfront is a 1,100,000-sq.-ft. mixed-use development
made up of office, residential and retail elements. It is located on an 11.3 acre
site bordering the Arizona canal in downtown Scottsdale. Phase I consisted of
two and three-story office and retail buildings totaling 200,000-sq.-ft. Retail
space is concentrated on the first and second floors with office space on the
second and third levels. Two stories of underground parking will provide for approximately
650 vehicles. The second phase consists of two residential towers housing 198
luxury condos. Each tower will rise to 13 stories, and features residences ranging
from 1,100 to 5,000-sq.-ft. The average unit sale price is $1.1 million. 4.
Red Mountain Freeway/ Loop 202: University to U.S.-60 Interchange Construction
Cost: $138.8 million Started: May 2005 (Interchange);
December 2005 (University/Southern) Target Completion:
October 2006 (Interchange); May 2007 (Univ./Southern) Owner: Arizona Department
of Trans. General Contractor: Pulice Construction, Inc. Engineers: AZTEC
Engineering (Interchange); Parsons, Brinckerhoff, Quade & Douglas Inc. (University/Southern)
Electrical Contractors: CS Construction; Contractors West Asphalt Paving:
Combs Construction Other Subcontractors: McNeil Brothers; Consolidated Rebar;
Coffman Specialties, Inc.; Carlson Masonry; Endo SteelThis project
encompasses a new 2.1 mile freeway extension north of University Dr. to south
of Southern Ave, a new one-mi. freeway section from Southern to Baseline avenues,
widening portions of US-60, and completion of directional ramps at Loop 202 and
U.S.-60. New freeway sections will be six-lane urban divided roadway with collector
distributor roads and will include a total of 15 concrete bridges between the
sections. Other construction includes 3.7-million cu.-yds. of excavation, 17 reinforced
concrete box culverts and 515,000 sq. ft. of retaining and sound walls. 5.
Hayden Ferry Lakeside Phase II, Edgewater and Bridgeview
Construction Cost: $135.4 million Started: Various,
beginning December 2004 Target Completion: Various through late 2007 Owner:
Hayden Ferry Lakeside, LLC/ SunCor Development Co . Architect: DFD CornoyerHedrick
(Phase II); IBI/HB Architects with Callison Architecture (Bridgeview & Edgewater)
General Contractor: McCarthy Building Companies Engineers: Civil Resources,
LLC; Caruso Turley Scott, Inc.; Friedhoff Civil Engineering; Cary Kopczynski
& Co, Inc. Phase 2 of Hayden Ferry includes a 12-story, 300,000-sq.-ft.
Class A office building, a three-story retail/office building and a four-level
addition to an existing parking structure. In addition, one level of underground
parking will sit below a 12-story office tower and retail/restaurant component.
Edgewater at Hayden Ferry Lakeside is the first of four residential towers planned,
each with its own name and identity. The 8-story, 40-unit condominium tower features
units ranging in size from 1,136 to 3,166-sq.-ft. Bridgeview at Hayden Ferry Lakeside
features 104 luxury condominiums in a 12-story tower, each with a private balcony.
The units will range in size from 1,100 to more than 5,000 square feet and will
be priced from the high $300,000 to $4.7 million. . 6.
Banner Gateway Medical Center Construction
Cost: $110 million Started: October 2005
Target Completion: May 2007 Owner: Banner Health System Architect: NBBJ
Architecture/ The Orcutt/ Winslow Partnership General Contractor: McCarthy
Building Companies, Inc. Electrical: Delta Diversified Electric Mechanical:
University Mechanical Steel: Schuff Steel Plaster/ Drywall: Pete King
Corp. Banner Health's new 360,000-sq.-ft. greenfield Gateway Medical
Center in Gilbert consists of a five-story in-patient tower and a two-story diagnostic
and treatment building with a full basement. The facility will include 171 beds.
7. Mountain Vista Medical Center
Construction Cost: $108 million Started: September
2005 Target Completion: Spring 2007 Owner: Iasis Health Care Architect:
Perkins & Will / CRA General Contractor: R.J. Griffin & Company Structural
Engineer: L.A. Fuess Partners, Inc. Electrical: Enterprise Electric Mechanical:
Midwest Mechanical Contractors Concrete: Suntec Concrete Steel: Cives
Steel. This project is a 370,000-sq.-ft., three-story, 174-bed hospital
and has been designed for a future vertical expansion. The structure is steel
with both a masonry and EIFS exterior. The hospital is intended to be a full service
facility including women's services, labor and delivery, general and cardiac operating
rooms, cath labs, endoscopy, MRI and CT, physical therapy, an Emergency Department,
ICU, bariatrics wing, and a geriatrics psychiatry wing. 8.
Apollo Riverpoint Center Construction Cost:
$107.7 million Started: September 2005 Target
Completion: June 2007 Owner: Apollo Development Architect: Carpenter-Sellers/SmithGroup
General Contractor: Sundt Construction, Inc. Engineers: SmithGroup; Caruso,
Turley, Scott; Dibble & Associates. The Apollo Riverpoint Center will
serve as the future headquarters for the University of Phoenix Online, and is
located at 32nd Street and Interstate 10. The 38-acre campus will include one
10-story office building and two six-story buildings including a full-service
kitchen and dining facilities. The 600,000-sq.-ft. office buildings are cast-in-place,
post-tensioned concrete frames, clad in copper, glass and precast panels. Two
pre-cast parking structures will accommodate 4,500 vehicles. 9.
ASU McAllister Residential Village Construction
Cost: $89 million Started: February 2005
Target Completion: August 2007 Owner: Arizona State University Planning &
Construction Architect: Gould Evans Associates, LC; Machado and Silvetti Associates,
Inc. CM at Risk: CORE Construction Services of Arizona Structural Engineer:
Paragon Structural Design Electrical: Wilson Electric Mechanical: HACI
Mechanical Contractors Concrete: Concrete Systems, Inc. Steel: S & H
Steel The McAllister Academic Village will create facilities for both
living and learning, mixing 1,500 beds with classroom, computing, and tutoring
space. The project provides 508,000-sq.-ft. for residential space, 57,400 sq.
ft. of academic space and another 20,000 sq. ft. of retail/service space. The
residential space is clustered around a two-story lounge with a glass curtain
wall that allows access to an exterior courtyard. The new Campus Math Solutions
Center and Campus Advising Center straddle the outdoor student space. 10.
The Ironwood-Gantzel Roadway Improvement Project
Construction Cost: $77 million Started: June
2005 Target Completion: January 2008 Owner: Pinal County Department of
Public Works CM at Risk: Sundt Construction, Inc. Engineers: Kimley-Horn
& Associates, Inc The Ironwood-Gantzel Roadway Improvement Project
is located primarily in the northern unincorporated region of Pinal County. Sundt's
scope of work includes providing pre-construction services for the seventeen mile
road widening through the Ironwood-Gantzel Road corridor that extends from U.S.-60
to Hunt Highway. The construction package will contain four phased packages: Phase
A will be complete in early June 2006, and Phases B and C will start In early
May 2006. Phase D will start early 2007. 11.
Sky Harbor Inline Explosive Detection System Construction
Cost: $75 million Started: December 2005
Target Completion: Summer 2007 Owner: City of Phoenix Aviation Department/Transportation
Security Administration Architect: DWL Architects + Planners, Inc. General
Contractor: Turner Construction Engineers: kpff Consulting Engineers; Stantec
Consulting; LSW Engineers Arizona, Inc. Sky Harbor International Airport's
explosive detection system project includes a sophisticated automated baggage
conveyance system and building support facilities. The system screens all outgoing
passenger luggage for the entire airport. The project includes work in nine separate
locations throughout Sky Harbor Airport on both the land side and high security
air side areas. Approximately half of the construction costs are for the automated
baggage conveyance equipment design and installation. 12.
Superstition Freeway (US-60) Gilbert to Power Roads
Construction Cost: $73.7 million Started: October
2005 Target Completion: Spring 2007 Owner: Arizona Department of Transportation
Design: Parsons Brinkerhoff General Contractor: FNF Construction, Inc.
Electrical: CS Construction Steel: Dunn del Re Steel Other: Breinholt
Contracting; Carlson Masonry; Recon, Inc.; Meadow Valley Contractors FNF is performing
road improvements, widening the freeway and adding rubberized asphalt to the U.S.
60 Superstition Freeway from Gilbert to Power Roads. This project is part of the
Superstition Freeway Improvement Plan that began in 1993 after the Federal Highway
Administration, ADOT and the Maricopa Association of Governments determined that
there was an immediate need for improvements to the freeway due to mass development
in the surrounding areas, as well as environmental concerns. Work on the project
includes sound wall installments, embankments, excavation and the widening of
three concrete bridges in the area. This massive widening project is especially
challenging, as the freeway is to remain open during construction. 13.
Splendido at Rancho Vistoso Construction
Cost: $70.4 million Started: April 2005
Target Completion: September 2008 Owner: Tucson Mather Plaza LLC Architect:
Solomon Cordwell Buenz & Associates General Contractor: The Weitz Co.
Engineers: WLB Engineers; TLCP Structural, Inc. The development is
Tucson's first true continuing care retirement community and will be a 27-acre
development for adults 55-plus with services and amenities comparable to a fine
resort. Amenities of the 625,589-sq.-ft. project will include fine dining, a state-of-the-art
fitness center and spa, an 18-hole championship putting course and concierge.
Splendido will feature 240 independent residences that include terrace homes and
villas with private garages, as well as an on-site health center, assisted living
apartments, memory-support and skilled nursing suites, library, wine room, billiards,
restaurant, multi-purpose room and an arts and crafts room. 14.
Banner Baywood Medical Center Patient Tower
Construction Cost: $65 million Started: November
2004 Target Completion: September 2006 Owner: Banner Health Arizona
Architect: Westlake Reed Leskosky Architects CM at Risk: Layton Construction
Co., Inc. Engineers: Evans Kuhn Associates; Paul Koehler Consulting Engineers,
Inc. Electrical: Delta Diversified Electric Mechanical: Tri-City Mechanical
Concrete: Suntec Concrete Steel: Skyline Steel The project includes
a new 7-story, 123-bed tower addition, a new wing to house the imaging department,
several new support buildings including a 640-space parking garage, and an extensive
remodel to the existing tower. Hospital functions continued uninterrupted during
construction with minimal disruptions to service delivery. New construction also
includes a 26-bed intensive care unit, two operating rooms and a stroke and cancer
center to the medical center located in east Mesa. 15.
Westgate City Center Construction Cost: $62
million Started: Summer 2005 Target Completion:
September 2006 Owner: Ellman Companies Architect: Development Design Group,
Inc.; Kurt D. Reed Associates General Contractor: Perini Building Company,
Inc. Engineers: Paul Koehler Structural Engineers, Inc.; WET Design Electrical:
Bergelectric Corporation Mechanical: Midstate Mechanical, Inc. Concrete:
Progressive Concrete Works, Inc. Steel: Schuff Steel Phase one
of Westgate City Center includes 10 buildings on 223 acres, totaling 500,000 sq.
ft. of retail, dining office and entertainment space. Two of the buildings will
be four stories, plus one level of underground parking. Four additional structures
will provide more retail space, while restaurants will occupy the two buildings
closest to the Glendale Arena and one large plantation-style building in the center.
Each structure has its own unique façade, mixing various elements such as white
concrete, aluminum storefronts, wood trellis structures, architectural masonry,
EIFS, glass and steel. One of the most unique aspects of Westgate is the signage,
including six immense, 100-ft.-tall signs featured prominently throughout the
site. 16. Countrywide at Chandler Commons
Construction Cost: $55 million Started:
January 2005 Target Completion: March 2006 Owner: Countrywide Home Loans Inc.
Architect: DMJM + Harris General Contractor: Hunt Construction Group
Civil Engineer: Evans Kuhn Associates Electrical: Wilson Electric Mechanical:
Tri-City Mechanical Concrete: Riggs Concrete Steel: Able Steel Fabricators
The mortgage and financial services company Countrywide is expanding its Arizona
operations with two new buildings at a 26-acre site which is part of the Chandler
Commons Office Park. Each building contains 175,000 sq. ft. of space and will
eventually hold up to 2,500 employees. The class A office space and an adjacent
850-space parking garage will also offer employees a full-service cafeteria and
fitness center. 17. Coronado High School
Construction Cost: $47 million Started:
Fall 2005 Target Completion: Spring 2008 Owner: Scottsdale Unified School
District #48 Architect: DLR Group CM at Risk: Adolfson & Peterson
Engineers: Hubbard Engineering; DLR Group Electrical: JEN ELECTRIC Mechanical:
Russell A.C. Concrete: L.R. Cowan Concrete Steel: W&W Architectural Metals
The 307,850-sq.-ft. Coronado High School campus design arranges the two-story
classroom building to enclose a courtyard. The circulation courtyard separates
the classroom building from the gymnasium, cafeteria, auditorium/performing arts
buildings and vocational classrooms, creating active and passive areas. The exterior
materials of the new building will be contextually compatible and respective of
the diversity of the Coronado Heights neighborhood. The auditorium and outside
amphitheater will accommodate large performance activities with easy public access
from the main parking lot and streets. 18.
Pinal County Adult Detention Facility Construction
Cost: $43.9 million Started: January 2005
Target Completion: May 2006 Owner: Pinal County Department of Public Works
Architect: Durrant General Contractor: Okland Construction Engineers:
Durrant; Norman Engineering Group Electrical: Wilson Electric Mechanical:
Conwest; HACI; Ryan Mechanical Concrete: Okland; Ceco; Jones Concrete
Steel: American Steel Masonry: Maverick Masonry The Pinal County
Adult Detention Expansion, located at the north edge of the Town of Florence,
is part of a Pinal County Judicial master plan developed by Durrant Group. The
cast-in-place concrete superstructure and masonry cells are supported by a foundation
of 198 piers that extend 35 feet deep into the ground. The 177,022-sq.-ft. expansion
used over 20,000 c.y. of concrete and 300,000 concrete blocks. The structure is
built to accommodate 1,052 inmates with minimum, medium and maximum security components.
Cells are arranged in a double tier layout over three stories. The project also
included a new master control room and a complete security electronics upgrade
to the housing units and staff areas in the existing 100,000-sq.-ft. facility.
This extensive security upgrade will replace an antiquated system and failing
components to create a state-of-the-art facility, and increase the safety, productivity
and efficiency of Sheriff's Office personnel. 19.
Arcadia High School Construction Cost: $43.6
million Started: October 2005 Target Completion:
December 2008 Owner: Scottsdale Unified School District #48 Architect:
The Orcutt/Winslow Partnership General Contractor: DL Withers Construction
Engineers: Atherton Engineering; Caruso Turley Scott, Inc. Electrical: Secon
Specified Electrical Contractors Mechanical: All Temperature Control Concrete:
Tpac; Concrete Structures Steel: Triad Steel The redevelopment
of the Arcadia High School campus presented a rare opportunity to reintroduce
a modern facility into an established Phoenix suburban neighborhood. The goal
of the Arcadia High School redevelopment project was to create an architectural
solution supportive of the school's curricular goals and respectful of the Arcadia
neighborhood heritage. The project creates a modern high school campus echoing
traditions of the Arcadia neighborhood that accommodates a diverse student body
of 1,400 students with a wide range of socio-economic and ethnic backgrounds while
integrating a departmentalized academic structure while providing a safe and secure
environment for students to learn and grow. 20.
Raintree Corporate Center Construction Cost:
$41 million Started: September 2005 Target
Completion: February 2007 Owner: Cavan Real Estate Investments Architect:
Patrick Hayes Architecture General Contractor: Summit Builders Engineers:
Erickson Meeks Engineering; Paul Koehler Consulting Engineers, Inc. Electrical:
Secon Specified Electrical Contractors Mechanical: HACI Mechanical Concrete:
Suntec Concrete; Tpac; Bownan Brothers Concrete Steel: Noble Steel, Inc.
The Raintree Corporate Center will encompass 356,000-sq.-ft. within two three-story
office buildings on an 11.3-acre site. The project also includes a 558,000-sq.-ft.,
six-level parking structure with three levels above and three below grade that
will accommodate 1,321 vehicles. Click
here for More 2005 Top Projects>>
|