| U.S. 95 Widening
Nears Completion
by Tony Illia
The $540 million, nine-mile-long U.S. 95 widening project in northwest
Las Vegas is nearing completion. The seven-year, multi-phase undertaking will
increase freeway capacity to ten-lanes from Martin Luther King to Rainbow Boulevards,
and to six lanes from Rainbow Boulevard to Craig Road. One lane in each direction
will also service High Occupancy Vehicle (HOV) travel.
|
The project suffered a scheduling setback when The
Sierra Club filed a lawsuit in 2002, two years after work had started. The suit
alleged that the government's environmental impact study didn't take into account
health risks caused by certain pollutants, and wanted the FHA to take into account
claims that highway pollution increases the risk of cancer in nearby residents.
Although an injunction was rejected by U.S. District Judge Philip Pro
in March 2004, the environmental group prevailed at the Ninth Circuit Court of
Appeals in San Francisco. Both sides reached a June 2005 settlement that enabled
major work to move forward.
The two remaining pieces are now both under
construction, including the $63.2 million Project 3C, which reconstructs the U.S.
95 bridge over Rancho Dr. and the connector ramps to and from I-15. A new on-ramp
from Martin Luther King to northbound U.S. 95 and a new off-ramp from southbound
U.S. 95 to Martin Luther King will also be constructed.
North Las Vegas-based
Frehner Construction Co. is the general contractor, with Parsons Brinkerhoff,
New York, as the designer.
Las Vegas Paving Corp., meanwhile, is performing
the $94.8 million Project 4B/5 widening featured in this issue. Both projects
are expected to finish by fall 2007. An overview
of the separate bid packages for the U.S. 95 Widening Project in Las Vegas.
Project 1A Widen from Washington to Cheyenne
Ave. Completed: Sept. 2001 Construction Cost: $13.9 million Design:
Sverdrup Civil Contractor: Meadow Valley Contractors Project
1B Widen from Cheyenne Avenue to Craig Road Completed: June 2002 Construction
Cost: $9.2 million Design: Sverdrup Civil Contractor: Las Vegas Paving Project
2A Replacement bridge at Torrey Pines Dr. Completed: April 2002 Construction
Cost: $3.6 million Design: Parsons Transportation Group Contractor: Crystal
Cascades
Project 2B Replacement bridge at
Decatur Blvd. and Valley View Blvd. Completed: September 2003 Construction
Cost: $20.4 million Design: Parsons Transportation Group Contractor: MMC
Inc. Project 2C & 2D Summerlin Pkwy. /
Rainbow Blvd. Interchange Completed: August 2005 Construction Cost: $42
million Design: PBS&J Contractor: Frehner Construction
Company
Project 3A S.R. 599 Rancho Drive Storm Drain Completed: June 2004 Construction
Cost: $5.8 million Design: Parsons Brinckerhoff/ VTN Contractor: Las Vegas
Paving Company Project 3B Storm Drain and Sound
Walls Completed: February 2005 Construction Cost: $16 million Design:
Parsons Brinckerhoff Quade & Douglas Contractor: Frehner Construction
Company
Company Project 3C Interchange and
ramps at Martin Luther King Blvd. and Rancho Dr. Estimated Completion: Fall
2007 Construction Cost: $63.2 million Design: Parsons Brinckerhoff Quade
& Douglas Contractor: Frehner Construction Co.
Company
Project 4A Storm Drain and Sound Walls Completed: September 2005 Construction
Cost: $19.5 million Design: Parsons Transportation Group Contractor: Meadow
Valley Contractors
Company Project 4B/5 Widen
east of Valley View Blvd. to Rainbow Blvd. Interchange Estimated Completion:
Fall 2007 Construction Cost: $94.8 million Design: Parsons Transportation
Group/ PBS&J Contractor: Las Vegas Paving
Source: Nevada Department
of Transportation Click
here for Next Highway Construction Feature>> |