| When the
Well Runs Dry Water Treatment Plant Brings Safe Water to Albuquerque
By
Scott Blair For much of its history, the city of Albuquerque was
unconcerned with the level of water usage. City engineers reported a nearly
limitless supply of groundwater replenished by the Rio Grande River.
|
However, over time and after several long-term city,
state and federal studies, city officials came to realize that almost half the
water pulled from the ground was not being replenished. In 1997, the city adopted
its current water usage plan, which calls for diversion of water from the San
Juan River through the San Juan-Chama River Project, a series of conveyance channels,
diversion dams and pipelines to bring the water over the continental divide and
into Albuquerque's Rio Grande River.
Construction started on the approximately
$500 million project in 2004 and should continue under multiple contracts through
2008.
The city has owned the stake in this water source since the Upper
Colorado River Compact was drawn up in 1922, but until now has either stored its
allotment or leased it to other users.
The keystone of this massive public
works project is a $160 million water purification plant designed by the Albuquerque
office of CH2MHill that will process the diverted water into safe drinking water.
The 80-acre facility will be home to a mind-boggling array of nearly two
dozen buildings, drying beds, tanks and miles of piping.
"When planning
for this project, we divided it into major areas and handled it as four independent,
though coordinated, areas," said Luis Ventoza, vice president of PCL Civil
Constructors Southwest of Phoenix, the general contractor on the project.Triad
Builders was brought on as a 20 percent partner. The Albuquerque-based firm assisted
with providing local subcontractors and contacts in the area, Ventoza said.
The
three-year construction project began in 2005.
The water will be sent into
two 50-million-gallon settling ponds that will separate the sediment out with
the aid of chemicals.
The ozone contactor building will oxidize any organics
in the water and then the filtration facilities will utilize granular-activated
carbon to remove any remaining organics.
The treated water will then sent
into the finished water storage tanks. "Most of the structures are lined
up on an east/west axis," said Howard O'Connell, construction manager for
PCL/Triad. "An 84-in. main water line and two smaller lines will be buried
under 10 ft. of concrete from three, 1,800-yd. pours. Piping will come up through
the concrete into the various filtration systems in the buildings above ground."
In
addition to the 84-in. line, the project utilizes 66-in. and 72-in. pipe, supplied
by Northwest Pipe of Phoenix. "The pipe comes in 50-ft., straight lengths,
and every joint is welded inside and outside and then air-tested to make sure
it doesn't leak," Ventoza said.
There are a huge number of fittings
on the project because the water will be piped to and from so many separate structures,
Ventoza said. "Our team is probably spending most of their time with the
fittings, making sure the angles and coordinates match," he said.
"One
of the things we do that's different from a lot of other contractors is we produce
a three-dimensional model of our yard piping. It allows the team to take sections
of the model directly into the field, so if there are any conflicts they are identified
early and given to the engineer for a solution."
The concrete shortage
in New Mexico caused some major headaches for the construction team. "Early
in the project we were hit by an allocation which cut our scheduled concrete production
in half," Ventoza said. "Right now we are playing catch-up.
"With
the help of the city, we were able to negotiate with our local concrete supplier,
LaFarge of and they increased our allotment. A lot of work we were planning on
doing earlier is happening now in the winter, so that's hurting our schedule."
Even still, the three-year project is only about two or three months behind
schedule, Ventoza added.
Key Players
Owner:
Albuquerque Bernalillo County Water Utility Authority General
Contractor: PCL Civil Constructors/ Triad Builders
a joint venture Design: CH2MHILL Concrete:
PCL Civil Constructors Steel: D'Ambra
Steel Electrical/Mechanical: McDade-Woodcock,
Inc
Click here for next Albuquerque Activity Report Feature>>
|