| Movin'
on Up The Residences at 2211 Camelback
By
Scott Blair The Biltmore area of the Camelback Corridor in Phoenix
is quickly becoming one of the most desirable real estate locales in the state,
if not the country. Though the rewards are ample for the developer who builds
here, limited available land is making construction of new residential buildings
ever tougher.
|
A new condo development, the Residences at 2211 Camelback
tackles these concerns head on by utilizing a small piece of open land partly
occupied by a water retention area and surrounded by an existing office complex.
"The site is only a little over an acre and has two office buildings
flanking it, while abutting an existing parking garage," said Steve Bassett,
principal with Phoenix-based architect DFD CornoyerHedrick. "Getting all
of that to tie together, while maximizing the views, was the biggest challenge."
The
$42 million structure was designed with the greatest number of corner units possible,
defined as those having at least two exterior sides. "We are getting six
corner units by stepping and sliding the plan," Bassett said. "Rather
than doing a simple rectangle, we shift the units to expose more than one side.
This was done to take advantage of the views, which are exceptional especially
once you get above the surrounding office buildings."
The 12-story
cast-in place concrete structure will rest above four levels of underground parking
and features 90 units ranging from 1,900 to 4,000 sq. ft. The plaza-level deck
ties into the two existing office buildings to the north and west. "The
project is 100 percent sold out, so we will be doing tenant improvement for almost
all the units in addition to constructing the shell," said Ryan Heeter, project
manager with Tempe-based general contractor Residential Constructors, LLC, a wholly-owned
subsidiary of McCarthy Building Companies. Initial unit prices ranged from $500,000
up to $2.5 million.
Buyers were able to select from a menu of interior
finish options which were put together along with a schedule of deadlines by the
contractor at the beginning of the project, Heeter said. "One nice thing
is that each unit is permitted separately, so if someone doesn't decide how they
want their wall layout, we can let that unit fall by the wayside and keep going.
It's not going to affect getting occupancy on the building for any of the other
individual units."
Extravagant choices made by some buyers include
a $50,000, 12-head shower complete with LED lighting and a $2,000 toilet that
sits out in the middle of the bathroom floor, Heeter said.
Roof amenities
include a pool and sundeck, barbeque areas, fire pit and entertainment terrace.
"We've taken great measures to make sure the pool's >> waterproofing
is tested, documented and that we avoid any penetrations underneath the pool area,"
Heeter added.
"The waterproofing is essentially a secondary bathtub
underneath the pool with drains so that it never leaks."
The roof
also houses some of the mechanical systems. "This project has somewhat of
a unique system because each condo unit is residential, but the backbone of the
system is commercial," said Gary Szymura, project manager for HACI Mechanical
Contractors of Phoenix. "The cooling towers, pumps, outside air-handling
units, condenser water piping and smoke-control systems are the same ones that
would be installed if the building was a commercial office building."
However,
each individual unit has its own heat pump, utilizing water circulated from the
main systems.
The exterior finish will receive three coats of Portland
cement stucco with an integral-colored finish coat to match the existing office
complex. Designers utilized floor-to-ceiling glass as often as possible, Bassett
said. Insulated, clear-tinted glass was used to keep the views unhindered.
The
construction team also had to harmonize with the center's existing landscaping.
"For the size of the site, the hardscape is pretty complex,"
Heeter said. "There's a mixture of stained concrete, cement pavers, built-up
landscaping beds and raised planters all the way up the driveway with date palms.
So in the next couple of months the landscape out here is going to change quite
a bit."
The roof will also receive six main planters housing trees
with numerous stand-alone pre-cast planters. Key
Players
Owner: The Patrinely
Group General Contractor: Residential Constructors,
LLC Architect: DFD CornoyerHedrick Electrical
Contractor: Wilson Electric Mechanical Contractor:
HACI Mechanical Contractors, Inc Concrete:
Ceco Concrete; McCarthy Building Companies Framing/ Drywall: Eliason
& Knuth of Ariz., Inc
Click here for next Residential Tower Construction Feature>>
|