| A Bridge to the Past
By K. Robert Wendel An old bridge with
unsafe ramps is making way for a brand new bridge in Tucson, with Hunter Contracting
of Gilbert, Ariz. teaming with the Pima County Department of Transportation to
reconstruct Veteran's Memorial overpass in southeast Tucson.
|
Work on the fast- track, $18 million project started in June, with the demolition
of the old Palo Verde Bridge on 44th Street and Alvernon Way.
"The
bridge was just too old," said Tom Kilargis, field engineering division manager
for Pima County. "It had the old style pin and hanger system that is subject
to corrosion."
The project involved an extensive amount of earthwork
to pull down the old abutments and build newer and larger abutments for the approaches
and bridges. The older bridge also had settlement issues, so crews brought in
borrow and re compacted the site.
But rains have slowed work. "The
goal from Pima County is to get this bridge done in 12 months," said Hunter
project manager Jeff Jones. "We are facing a double liquidated- damage standard
at 12 and 16 months, so we have to get it done."
The damages could
go as high as $2,500 a day. Jones said his crews have lost two weeks because
of the wet conditions in southern Arizona this year.
The project entails
building up new embankments, building five bridge spans and installing interchanges.
The bridge's largest span is a 77-ft. precast concrete- tub girder that spans
the railway track. Shorter spans include a 60-ft. section.
The total bridge
length is 350 ft. long with a 133-ft.- wide road deck. Plans call for four lanes
in each direction along with dedicated turning lanes.
"It was difficult
working around the railroad tracks, and the biggest challenge was the geometry
of the bridge, which is curved," said Anthony Gravagne, a project manager
with Tucson's Structural Concepts Inc., a structural engineering firm. "Because
of the track layout we to put the piers in the right place, so we ended up with
three different types of spans."
In addition to spanning the railroad,
the bridges also span channels of Tucson's diversion system. Engineers and contractors
teamed to value engineer the sections, saving money by using cast-in-pace concrete
arches on the smaller spans. The value-engineering team also saved money by using
a mechanically stabilized earth wall.
"The original design had abutments
that were designed to be full height, but we decided to use a mechanically stabilized
earth wall," Gravagne said. "We have steel straps running back into
the earth with little nodules every few inches.
The nodules interface
with the soils, we end up with a good connection and the walls and the trap function
as one element."
On the bridge decks, contractors will use two courses
of asphalt in two, 2.5-in. lifts. A friction coat of asphalt rubber will also
be used. Contractors will eventually use 19,000 tons of asphalt and 13,000 cu.
yds. of concrete.
As with many road projects in Tucson, art and architectural
features are a major part of the bridge design. Plans call for a stars and stripes
theme to celebrate veterans.
The project is scheduled for completion this
summer.
|