|
Getting a Recharge
By K. Robert Wendel
The city of Glendale, Ariz. is planning for a thirsty future
with the construction of an expanded wastewater treatment
plant near the Glendale Airport.
Crews from Sundt Construction started the $31.5 million, construction
manager at-risk project in January 2003. Contractors plan
to finish the 6 million gallon-a-day expansion in November.
When complete, this second phase features a peak processing
capacity of 16 MGD, with a constant flow of 10 MGD. The project's
first phase processes 4.3 MGD and depending on population
growth, a third phase may be constructed.
|
"Based on population projects, this should be enough,
but it's going to be close to the edge," said Thomas
Bolyn, senior plant operator at Glendale's West Area Water
Reclamation Facility. "This second phase pretty much
doubles everything."
The treatment plant takes wastewater from a 91st Avenue plant
main line, treats the water and then injects the finished
product into recharge basins for future use. The plant sends
the remaining solids back into the mainline, taking the sludge
to the 91st Avenue plant, where it is processed.
"This is sort of a weird plant," said Ben Herman,
a project engineer with Phoenix-based Nabar Stanley Brown.
"Regular wastewater treatment plants have a high point
and low point, but this one scalps a certain amount off the
line that is pretty much constant, so you don't have peaks
and valleys."
To treat the water, it first goes through a series of filters
to screen solid waste out. The water then passes through a
grit pump and basin that removes any remaining sediment. Water
then flows to aeration basins where its mixed with oxygen
and then through another filtration process using anthracite
filters. It's on to ultraviolet disinfection after that, and
then finally, it is injected into the ground.
"If you take a look at the water going into the plant,
it's gray and greenish," said Ed Martin, an engineer
with Malcolm Pirnie. "When it gets through the ultraviolet
disinfection system, you can actually see through the water
to the bottom of the basin.
That's how clean it gets."
The finished water is not potable, but it can be used for
irrigation, fountains and recharging the acquifer.
The expansion project entails a doubling or tripling of the
plant's components and equipment. Four, 35-horsepower generators
are getting replaced with seven, 250-horsepower generators.
New concrete aeration basins, screens and filters are also
planned.
One of the most challenging aspects of the project involved
the shut down, connection phase and start up of the expanded
plant. Crews worked 24 hours a day, seven days a week to accomplish
the work.
"The plant has to have a week of preparation for the
shut down and it takes two weeks to bring it back on line,
so you are talking about month where you aren't processing
anything," Martin said. "We actually finished 12
days ahead of schedule, which was a big achievement."
|