|
Hoover Dam Bypass - Nevada Approach
River Roadway
by Tony Illia
Activity is humming along on Arizona's roadway approach to
the Hoover Dam Bypass Bridge, an alternate crossing over the
Colorado River that is expected to greatly relieve traffic
over the dam''s existing two-lane highway, which sees more
than 13,000 vehicles a day.
The U.S. Highway -93 route is a major commercial corridor
identified in the North America Free Trade Agreement route
between Mexico and Canada. But since the terrorist attacks
of Sept. 11, truck traffic over the dam has been rerouted
23 mi. away, costing the industry an estimated $30 million
annually.
|
The Federal Highway Administration is awarding projects
to fast-track bridge construction. In February 2003, >>
a joint- venture of two Arizona firms, R.E. Monks Construction
Inc., of Fountain Hills and Vastco Inc. of Chino Valley, landed
the $21.4 million Arizona approach.
R.E. Monks serves as project manager, overseeing the excavation
and paving, while Vastco is responsible for the structures.
It's the first of four federal contracts needed to complete
the 1,900-ft.-long, four-lane bypass bridge, which also includes
4.3 mi. of accompanying roadway.
The rugged topography, which consists of tuff and basalt rock,
has required some tricky excavation. Subcontractor Western
States Contracting Inc., of Las Vegas performed 1.7- million-
cu. yds. worth of excavation. And due to the geology, the
rock removal entailed drilling and blasting in a piecemeal
fashion, carefully carving out the mountainside to the needed
depth and angle.
The material was then crushed and used as an earthen embankment
for a 1.8-mi. long, four-lane asphalt highway. Combs Construction
Co. Inc., of Peoria, Ariz., is the paving subcontractor.
"The steep terrain was an initial challenge," said
Pete Young, R.E. Monks' project engineer. "As far as
the overall scope, it's a pretty simple project. At least,
there aren't a lot of utilities in the way."
The project calls for a 1-mi. long, two-lane frontage road
to divert traffic while the bridge is under construction.
A total of 6,000 tons of asphalt will be used to complete
the roadways. Additionally, the job calls for two major bridge
structures: a full diamond interchange, plus another 902-ft.-long,
90-ft.-wide crossing.
The 16.7-ft.-tall interchange has 1,300-ft.-long ramps cut
into the mountainside. It will enable two lanes of traffic
to flow in each direction at Old Kingman Wash Road, which
serves as a gateway into the Lake Mead National Recreation
area.
The more challenging four-lane bridge crosses over a 160-ft.-deep
ravine. The seven-span structure is supported by six tapered
piers. There are 77 pre-stressed, 128-ft.-long concrete girders
that sit atop pier abutments.
"Each of the girders weighs 132,000 lbs.," said
Tim Kempkes, Vastco's project engineer.
With roughly 11 girders per span, Vastco used seven different
cranes to maneuver the pieces into place, ranging from a Link
Belt 250-ton crawler crane with 200- ft. of boom to 22-ton
Grove hydraulic crane. Jake's Crane & Rigging International
of Las Vegas was the crane provider.
"We had to come up with a complex scheme to place them
in each instance," Kempkes said. "Due to the wind
and conditions, we would pick-up some girders and change their
location in mid-air in order to properly place them."
About 11,000- cu. yds. of concrete will be used to complete
the bridges. Casino Ready Mix Inc., of Las Vegas, is supplying
the concrete. The median concrete mix is 7,500 psi, or nearly
double the strength of most structures.
Other contract work calls for 2,000 lin. ft. of cast-in-place
box culvert, plus 4,400 lin. ft. of corrugated metal pipe.
There is also 17,000 lin. ft. of game fencing to protect natural
wildlife in the area, including big horn sheep and desert
tortoise.
"We are really pleased by the work of the Monks-Vasco
team," said Dave Zanetell, the highway administration's
project manager. "They have played an important part
in getting the overall bypass started."
The Monks-Vasco team expects to finish its project well in
advance of its Oct. 15 deadline. But funding delays from the
slow reauthorization of Transportation Equity Act for the
21st Century, the federal road and highways bill that expired
last year, have pushed back the bridge's final completion
date.
Initially, the $235 million project was to open by 2007, but
that has been adjusted for a 2008 completion.
"We are hopeful that the remaining funds will come this
summer, and if that is the case, the bridge portion will advertise
in June," Zanetell said.
>ADOT Overview
>Where the Rubber Meets the Road
>Connecting the Communities
>I-10/I-19 Interchange
>Hoover Dam Bypass - Nevada Approach
|