|
Perini's Power Play
New Arena Erected in 17 Months
By K. Robert Wendel
It's been a fast and furious 17 months but the blades are
on the ice at the Glendale Arena, the new home of the National
Hockey League's Phoenix Coyotes.
The construction team, led by Perini Building Company, wrapped
up the 18,000-seat arena in time for the Coyotes to begin
playing in December.
Although slowed by weather that dumped more rain in 10 days
than Phoenix saw in 2002, contractors were able to complete
the project on time.
"To my knowledge, this is the fastest project ever designed
and constructed for an NBA or NHL arena," said architect
Jack Boyle, project manager for Kansas City, Mo.-based HOK
Sport + Venue + Event. "There's a triangle we have to
deal with, whether it is budget driven, schedule driven or
quality driven, it depends on the owner's priorities.
This project is driven by all three."
|
Ken Schacherbaur, Perini project manager, said the key to
the fast construction was the arena's design. The hockey arena
boasts more than 75,000 sq. ft. of clear span space, giving
every seat in the house an excellent view of the ice rink
and floor. This 75,000-sq.-ft. "high" ceiling bears
on four massive "super columns" connected by two,
330-ft. long, 20-ft. tall, 200 ton trusses. Ten in-fill trusses
200-ft. long and ranging between 31 and 59 tons will complete
the high roof section.
Once the super columns were raised and crews started work
on the exterior concrete bearing columns, "it was a matter
of the steel crews chasing the concrete crews around the arena,"
Schacherbaur said.
A "low" roof section will skirt around the high
roof and bear on the structural exterior columns. Two, 220-ton
cranes were simultaneously needed to lift the large trusses.
A rubber membrane roof system caps off the project.
"It's a pretty complex roof structure because the high
main roof only bears on four points, but it made the roof
simpler to fabricate and erect," said project estimator
Greg Peterson of Kansas City, Mo.-based Havens Steel. "Those
four columns are massive, heavy columns, so when you tie in
the low roof, the load gets distributed out to the concrete
perimeter columns."
Owned by the city of Glendale and leased to Phoenix businessman
Steve Ellman and the Arena Development L.L.C. group, the new
arena promises to be a premiere place for NHL fans to catch
the high intensity action, as well as a concert venue and
multipurpose center. The Glendale hockey arena anchors a 224-acre
site that will eventually feature millions of square feet
of development. The arena will sit on 15.1 acres of a 60-acre
footprint, with approximately 40 acres of on-grade asphalt
parking lots.
The new arena sits across from the future Arizona Cardinals
stadium, which is under construction. The hockey arena project,
which is a construction manager at-risk contract, featured
a guaranteed maximum price of more than $200 million. Another
$25 million is budgeted for fixtures, furniture and equipment.
"The design team spent a lot of time making sure the
facility is very adaptable to multiple uses," Schacherbaur
said. "A lot of thought went into the acoustic system
and there are also three configurations for a concert stage.
The arena is also capable of a basketball set up."
Designers began with a working model that was proposed for
a Scottsdale location, but after that site fell threw, some
redesign was needed for the Glendale site.
Preliminary design work started in fall 2001, but really began
in earnest in January 2002.
Crews started site work in June, pouring foundations and excavating
for the hockey rink, which is 30-ft. below grade. Phoenix-based
Buesing Corp. performed the foundation work, while Construction
70 of Phoenix excavated 225,000 cu. yds. of dirt.
Apache Pipeline of Phoenix also started on $30 million in
utility work for future retail and other development on the
224 acre site.
"One of the more interesting aspects of the project design
is aesthetics, because this project has to mesh with surrounding
development," Boyle said. "The larger challenge
with a building of this size and scale is making it fit with
one- and two-story retail projects."
Lots of Concrete, Steel
The new arena uses more than 2,500 tons of structural steel,
most of which is in the roof system. More than 32,000 cu.
yds of concrete, or enough to build 5,333 residential driveways,
will be used on the project. Perini Building Companies self-performed
the concrete work.
"Any time you self-perform work, it's a double-edged
sword," said Perini general superintendent Mike McLean.
"Concrete represents 14 percent of the project, so it's
a big undertaking. You like the control, but it creates a
lot of coordination headaches."
The seat risers and seating are all constructed of precast
concrete, along with some columns and raker beams in the arena.
The precast seating allows for a quick and simple installation,
according to Clint Calvert, vice president and general manager
of Phoenix-based Coreslab Structures.
"Stadium jobs are not straightforward jobs," Calvert
said. "They take an awful lot of coordination and an
awful lot of design work to make them turn out well."
Crews from Consolidated Rebar will tie approximately 4,500
tons of rebar, some of which is 2-in., No. 11 rebar, in just
eight months.
"It's a pretty intense job. It's almost like a design-build
project," said Scott Murin, vice president of Consolidated
Rebar of Phoenix. "The design is barely ahead of construction,
and actually construction has caught the design a few times."
Keeping it Cool
A 400-ton, variable drive chiller unit will provide comfort
cooling for offices, concessions and other areas when the
arena is not in use, while two, 1,000-ton constant volume
units will keep the arena cool during events. Four large air
handlers, capable of moving a 110,000 cfm each through 8-ft.
ducts, will supply the bowl.
Another 200 fan coil units will service the rest of the building,
which features more than 600 plumbing fixtures. Builders said
the design exceeds the ratio of bathrooms required by city
and state code.
"It's been very challenging to fit 10 lbs. of stuff into
a 5 lb. bag," said John Anderson of University Mechanical
and Engineering Contractors. "Ceiling heights are very
low, so space is at a premium. This building alone has 30
miles of pipe."
The ice floor also features miles of piping carrying chilled
brine water that freezes the concrete. Water is applied with
a hose, gradually building up layers of ice.
In the arena's interior, architects called for a variety of
finishes, with a utilitarian finish for concourses and events
levels, some nicer finishes in the public areas, and some
high end finishes in the 88 luxury sky boxes with 16 seats
each. A club lounge at the suite level will hold another 500
people. In addition to the club lounge, there will be 10 concession
stands and a commissary for centralized food preparation.
"There's a lot of work taking place out here," Schacherbauer
said. "It's nice working on the arena because it is the
sparkplug that is going to make this development work. This
is going to be the centerpiece."
|