|
With more than 35 million passengers streaming through its
gates each year, Phoenix's Sky Harbor International Airport
is one of the largest and busiest airports in the nation.
And with traffic projected to increase to nearly 60 million
by 2015, airport officials are working to keep abreast of
the growth and also deal with increased international traffic,
with European carriers such as British Airways and Lufthansa
offering non stop service to London and Frankfurt, Germany.
Crews from the Phoenix office of McCarthy Building Cos. are
wrapping up work on one project designed to handle the growing
international traffic load, a new, $16 million walkway for
travelers arriving from overseas. The new walkway will provide
increased security and smoother immigration and customs controls
for international passengers.
"The idea is to get the international passengers out
of the terminal without them mixing with the domestic passengers,"
said Steve Rao, vice president of Phoenix-based DWL Architects
+ Planners Inc., which along with Phoenix-based APMI, designed
the project.
"It turns into a hassle for the Transportation Safety
Administration and U.S. Customs because international passengers
get mixed in with domestic passengers and then they (agents)
have to inspect all the bags."
The idea for the international passenger walkway was first
proposed more than 10 years ago, but after the Sept. 11, 2001,
terrorist attacks on America, work on the project was accelerated.
Although the project isn't large in terms of dollars, the
tight work site, logistics, security and the need to keep
the airport up and running made the job complex for designers
and builders.
"This is one of the tightest logistical challenges I
have faced in 25 years of construction," said McCarthy
project director Jim Meadows. "It's not the size of the
job or the components. It's logistics, trying to fit this
project in an existing airport while maintaining a secure
envelope."
Crews could only work after 10 p.m. at night, and since Sky
Harbor Boulevard divided the site in two, McCarthy had to
construct a man-bridge over the road to get workers and tools
between the two areas.
A very tight site with only 30 -ft. between the existing retaining
wall and the road meant designers and contractors had to cantilever
a four-story "vertical transport" building out over
Sky Harbor Boulevard. The four-story building features four
elevators and two escalators to move passengers from the below-grade
walkway to the bridge spanning Sky Harbor Boulevard.
The vertical transport building features a sloped glass curtain
wall with concrete columns angling out over the road below.
Seamless stainless steel tubes encase the concrete columns,
giving the structure a modern, clean look. Four, 5-ft.-dia.
concrete columns support the building's entire weight.
"We wanted to throw in a little new twist and the sloped
glazing adds more of an international flavor," Rao said.
"We did try to relate a lot of the materials so they
would be similar to the existing buildings."
The vertical transport building in Terminal 4 is connected
to the "B" concourse with a 20-ft.-wide, 580-ft.-long,
glass-enclosed walkway running parallel to Sky Harbor Boulevard.
McCarthy excavated a tunnel underneath the gates, which brings
passengers to the walkway.
"We tried to make the tunnel imprint as small as possible
because there were quite a bit of utilities and we wanted
to minimize interference with those existing utilities,"
said Tim Sepper of Phoenix-based structural engineers KPFF
Engineers Inc.
Since the elevation of the walkway was below an existing retaining
wall running along Sky Harbor Boulevard, contractors had to
shore up the wall while tunneling and building the walkway.
McCarthy subcontractor Bechco Inc. used concrete micro-piles
drilled 30- ft. to 40- ft. vertically through the retaining
wall's footing to shore it up. A landscaped strip will feature
cactuses and other native plants once the project is finished.
If we hadn't stabilized that wall, when we excavated, it would
have just come tumbling down," said McCarthy's Jeff Brown
of McCarthy.
A 180-ft.-long bridge over Sky Harbor Boulevard brings passengers
into the main area of Terminal Four. The bridge required construction
of an 8-ft.-diameter. concrete column - on top of an electrical
duct bank. The area was so tight that contractors had to knock
the flanges off the concrete forms to fit the column in and
cast it.
"Structurally, one of the most challenging parts of the
project was threading the bridge through directly above some
lower bridges," Sepper said. "We had a corner that
curved over the loading dock, so there were very few locations
to put columns in to support the bridge."
Contractors built grade beams underneath the duct bank and
then spanned them with steel grillage and No. 11 rebar. The
column was then built on top, although it is slightly off
set.
Phoenix-based Able Steel fabricated and erected more than
180 tons of steel, while Azteca Electrical of Phoenix performed
the wiring. T-PAC, also of Phoenix, placed 270 precast segments
in the project, including a 60-ft.-long, 36-ton piece using
a sliding counter balance beam to fit the segment between
the existing structures above and below.
"It's not your typical building, it's not your typical
bridge and it's not your typical tunnel," Sepper said.
"It's all of those things in a tight, almost impossible
site."
|